Yes you are correct. After update use Tools-> Store Period Performance and select financial date correspond to your update. That will keep you history.
In addition to Duy explanation. When creating Graph, Profile, S-Curve and spreadsheet tick Display Actual using Financial Period data to have a comparison from your plan and actual.
Rola,
Period performance and Financial period are used to keep the past period data (i.e. plan, actual, EV etc...) so it will not move when progress are updated. It keeps the history which is used for comparing Actual, Plan, EV etc... on Columns, Graph Profile, S-Curve and spreadsheet.
As per P6 help:
Store Period Performance
Using the Store Period Performance feature, you can track actual units and costs to date. For example, if you increase the actual this period by 50, the Project Management module increases the Actual to Date by the same amount. At the end of each financial period, reset the Actual This Period values of all activities and assignments to zero by choosing Tools, Store Period Performance. Resetting the Actual This Period values does not affect Actual to Date values; rather, it prepares you to begin tracking new use for the current period.
Storing period performance records actuals for the selected financial period along with earned value and planned value, so you can track previous periods and compare current and future trends. If past period data changes after you store period performance, you can edit the data in financial period columns of the Activity Table, Resource Assignments window, and the Resources tab of Activity Details.
Your projects may be scheduled to update every two weeks, monthly, or even quarterly. To track actual costs and progress recorded, update your schedule at the times established in the Financial Periods dictionary, then store period performance at the end of the update period and before the start of the next schedule update.
To see the past period performance data, you need to go to: Edit\User Preferences\Application\Colums\select financial periods to view in colums (then click to choose your financial periods from... to...)
then back to Activities workspace, call for Columns\Financial Period Value\ choose your assigned periods
Member for
19 yearsRE: Store period performance how to see past performance
Rola,
Yes you are correct. After update use Tools-> Store Period Performance and select financial date correspond to your update. That will keep you history.
Member for
15 years 11 monthsRE: Store period performance how to see past performance
so it works instead of saving a copy of each month update right?
so i need to enter dates of updating as fincail peroid then save it.
Member for
19 yearsRE: Store period performance how to see past performance
Haresh,
In addition to Duy explanation. When creating Graph, Profile, S-Curve and spreadsheet tick Display Actual using Financial Period data to have a comparison from your plan and actual.
Rola,
Period performance and Financial period are used to keep the past period data (i.e. plan, actual, EV etc...) so it will not move when progress are updated. It keeps the history which is used for comparing Actual, Plan, EV etc... on Columns, Graph Profile, S-Curve and spreadsheet.
As per P6 help:
Store Period Performance
Using the Store Period Performance feature, you can track actual units and costs to date. For example, if you increase the actual this period by 50, the Project Management module increases the Actual to Date by the same amount. At the end of each financial period, reset the Actual This Period values of all activities and assignments to zero by choosing Tools, Store Period Performance. Resetting the Actual This Period values does not affect Actual to Date values; rather, it prepares you to begin tracking new use for the current period.
Storing period performance records actuals for the selected financial period along with earned value and planned value, so you can track previous periods and compare current and future trends. If past period data changes after you store period performance, you can edit the data in financial period columns of the Activity Table, Resource Assignments window, and the Resources tab of Activity Details.
Your projects may be scheduled to update every two weeks, monthly, or even quarterly. To track actual costs and progress recorded, update your schedule at the times established in the Financial Periods dictionary, then store period performance at the end of the update period and before the start of the next schedule update.
Member for
15 years 11 monthsRE: Store period performance how to see past performance
HI
can body please explain a little bit about peroid peformaces? and finacial period?
and what is it main use?
Thanks.
Member for
16 years 5 monthsRE: Store period performance how to see past performance
Hi Haresh,
To see the past period performance data, you need to go to: Edit\User Preferences\Application\Colums\select financial periods to view in colums (then click to choose your financial periods from... to...)
then back to Activities workspace, call for Columns\Financial Period Value\ choose your assigned periods
Hope it helps,
Duy