If it is reduced by 15%, they will deduct the qty x £original rate. -- ok
but can you claim lost due to opportunity forgone and the rate adjusted? This is because say buying power for materials at 15% less than original order could loose the discount or none economic of scale purchase. The material ordered but not use?
Same with plant productivity, could you not claim less economic production too because the rate produced was based on the qty in the original contract and now less qty so rate is affected?
Member for
22 years 7 months
Member for22 years7 months
Submitted by Dayanidhi Dhandapany on Sun, 2006-12-24 08:02
If it increases by 15%, you will get the difference(between the original effective contract price and revised(due to variations)effective contract price)conversely if it decreases by 15%, they will deduct that money from the original effective contract price.
This clause states that on the issuing of taking over certificate for the whole of the works, including all the variations valued under sub clauses 52.1 and 52.2, if the contract price(excluding provisional items and allowance for day works)changes by 15% (may be an increase or decrease to the original effective contract price), then the engineer after the consultation with employer and contractor, such sum can be added or deducted from the contract price. which means if the variation is not exceeding 15% of the effective contract price, as per my understanding the contract sum may not be altered due to addition or omission of such works. so you will get the same lumpsum price in this case.
Member for
18 years 11 monthsRE: Variations Exceeding 15 Percent?
Hi!
Is the "decrease or increase" will be based from the Contractors Site & Overhead Costs? Needs further opinion on this regard.Thanks.
Member for
19 years 5 monthsRE: Variations Exceeding 15 Percent?
Hi
Just a thought.
If it is reduced by 15%, they will deduct the qty x £original rate. -- ok
but can you claim lost due to opportunity forgone and the rate adjusted? This is because say buying power for materials at 15% less than original order could loose the discount or none economic of scale purchase. The material ordered but not use?
Same with plant productivity, could you not claim less economic production too because the rate produced was based on the qty in the original contract and now less qty so rate is affected?
Member for
22 years 7 monthsRE: Variations Exceeding 15 Percent?
If it increases by 15%, you will get the difference(between the original effective contract price and revised(due to variations)effective contract price)conversely if it decreases by 15%, they will deduct that money from the original effective contract price.
Member for
18 years 11 monthsRE: Variations Exceeding 15 Percent?
How about if it increase or decrease by 15%, whats the procedure? Thanks.
Member for
22 years 7 monthsRE: Variations Exceeding 15 Percent?
This clause states that on the issuing of taking over certificate for the whole of the works, including all the variations valued under sub clauses 52.1 and 52.2, if the contract price(excluding provisional items and allowance for day works)changes by 15% (may be an increase or decrease to the original effective contract price), then the engineer after the consultation with employer and contractor, such sum can be added or deducted from the contract price. which means if the variation is not exceeding 15% of the effective contract price, as per my understanding the contract sum may not be altered due to addition or omission of such works. so you will get the same lumpsum price in this case.