Project Scheduling

Manager - Planning and Control, AQUA DESIGNS INDIA PVT LTD, Chennai, Integrated Water Supply Scheme - Bihar - BUIDCO

START Date

1. Over all Project Planning and Control

2. Civil Contractor Finalisation and Schedule of completion discussion

3. Project Cost

4. Vendor/Contractor works expedition and Liasoning

5. Weightage Methodology and Physical Progress Calculation and Monitoring

6. Risk Logs

7. Critical path analysis and timely alarm to stake holders

8. Contractor Performance Monitoring'

9. Resource Planning

10. Progress Reports

11. Construction Coordination

Junior Project Controls Engineer, Washington River Protection Solutions, Tank Farms

A
Amanda Bui 👤 Member for 9 years 9 months
START Date
Experience Hours (Planning & Scheduling)
100
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
100

Project Controls Engineer/ Cost Analyst for Washington River Protection Solutions. Primary role is to forecast estimates to complete, create critical path schdeules, write variance reports, and create project management flow charts.

Senior Planner / Senior Planning Engineer, Techno Engineering & Associates, 1.Upgrading and Refurbishment of Sewage Treatment Plants 2.Multipurpose Hall & Sports Club (Handball Stadium)

START Date

To provide help to the Contractor’s Site planner for day to day planning issues and support the TEA Team in preparation of Forensic Delay analysis and EOT Claims.

·         Visit the site for progress monitoring

·         Review of the Monthly Progress Reports

·         Supervising the revision to the Baseline Program

PLANNING ENGINEER, GLOBUS CONSTRUCTIONS PVT. LTD., GREENOPOLIS

START Date
END Date
Experience Hours (Planning & Scheduling)
100
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
100

1. Preparing Monthly and Daily Progress Report

2. Analysis of Rates.

3. Preparing BOQ from Contract documents.

4. Analysis of Gap in Progress.

5. Resource Management.