Head of Planning & Controls Division, Nael & Bin Harmal Hydroexport, All projects in MENA region
PROFILE AT GLANCE:
PROFILE AT GLANCE:
Follow up & prepare EOT claims documents; the event, liability of the event, Contractualentitlement & compliance, cause & effect program and delay analysis. Responsible for the establishment & tracking of planning and scheduling for the project byusing Primavera. Monitor the project schedule and highlight any critical activity needs particular attention and Discuss it with project team to identify mitigating measures. Liaison with project team representative to track the Schedule based on key dates as
Al Harbi Industrial Development - Riyadh - KSA 4/2009 – To Date.
MY JOB IS ON CIVIL ENGINEER, AND I USE PRIMAVERA TO MAKE SCHEDULE FOR CONSTRUCTION
1- Maintain Master Schedule
2- Monthly Update for the Baseline Schedule
3- S- Curve
4- Comparison Between the baseline and the Update
5- EVM
Role: Project Controls – Lead Planner & Client Invoicing Engineer (Project Management)
High Rise Office Towers
Large Commercial Complexes
Commercial Buildings
Banks Buildings
Industrial Workshops / Factories
Feb 2011-Till Date: Project Planner at Worley Parsons
Job Profile:
· Update the Upstream Schedule (especially the mechanical packages and Trunk lines for upstream operations of Phase 1 QCLNG project) and then integrate into the overall schedule in a timely fashion to ensure accurate and efficient completion of the monthly progress updates
I have more than 10 years of work experience in a variety of different responsibilities such as project planner/planning engineer, cost planner/cost controller, project coordinator, investment analyst in oil & gas, construction and production projects
I have comprehensive skills in preparing detailed schedules of projects (WBS and activity definition, sequencing, resource & duration estimating) and preparing associated documents
Planning & Scheduling and Preparation of Reports ( Daily Report, Weekly Report and Monthly Report )