National Grid South East Electricity Substations Alliance (SEESA) - Planning team leader for a team of planning engineers based in SEESA HQ, Stokenchurch. Responsible for day to day team management, periodic team peer reviews, ownership of the alliance planning process, Primavera database administrator, full lifecycle planning, earned value analysis and reporting and portfolio planning (including ‘what if’ scenario planning). Deputise for the Planning Manager to provide ongoing cover for leave periods.
PROJECT NAME: CONSTRUCTION OF BMC-9712 MALL (Now Known As CAPITAL MALL) AND TWO 22-STOREY OFFICE BUILDINGS IN ABU DHABI- UAE.
PROJECT VALUE: AED 750 MILLION APPROX.
PROJECT MANAGERS: JACOBS INTERNATIONAL
JOB DESCRIPTION: AS A SENIOR PLANNEER, I HAVE BEEN RESPONIBLE FOR ALL PLANNING AND PROJECT CONTROL TASKS CONDUCTED DURING THE COURSE OF THE PROJECT. HAD BEEN ACTING AS MIDDLE TIER BETWEEN PROJECT CONTROL MANAGER AND JUNIOR PLANNER.
DEVELOPED MASTER SCHEDULE FOR THE PROJECT CONTAINING MORE THAN 7000 ACTIVITIES.
Responsible for the creation of a holistic view of the business portfolio of projects, supporting tendering exercises as part of a framework contract for M&E/Fit Out/Strip Out works based at a large defence contractor in Berkshire
Managed a £1m project to replace an aged asset that was crucial to the R&D part of the business.