project controls

Management of programmes and multiple projects and project managers

Engineering / Project Planning Lead, Fluor Daniel - Philippines, Habshan 5 Bid Proposal and Advance Engineering Project

START Date
END Date

Leads the Project Controls group for the entire project that provides project control functions for the Proposal Bid and Advance Engineering of Habshan 5 Project which includes but not limited to:

 

§  Development of pre-award proposal schedule in summary and detail.

§  Planning and scheduling of Engineering activities and deliverables.

§  Facilitate change management process.

Planning and Scheduling Engineer, Chiyoda Corporation, QCS Project Construction of Train-6 & 7

START Date
END Date

Construction Planning & Scheduling Engineer for the Project Director of the entire joint venture project. Provides construction planning support to the project management team which includes but not limited to:

 

§  Monitor and evaluate subcontractor’s level-4 schedule.

§  Conduct periodic feasibility study to determine the schedule’s discrepancies to Chiyoda’s standards.

P6 Planner, Carillion, and Others, Great Eastern Overhead Line Renewals, North London Line Railway Investment Project

J
James Bate 👤 Member for 14 years 8 months
START Date
END Date

 

January 2009 – May 2011 - P6 Planner – Carillion Rail – Signalling, Power and Coms

Based in Crewe and London.  Carillion has over 40,000 employees and an order book over £10bn

Assistant Manager - Project Controls, PT. Yasa Industri Nusantara, IFB II PGN Project Package

START Date
END Date
  • Prepare Project Master Schedule
  • Tracking Project Schedule (Daily)
  • Control Project Execution
  • Prepare Material Shipment Plan
  • Prepare Progress Report (Weekly & Monthly)
  • Analyze Problem & Prepare Corrective Action

Assistant Manager - Project Controls, PT. ZUG Industry Indonesia, Sintang Coal Fired Steam Power Plant

START Date
END Date
  • Prepare Project Master Schedule
  • Tracking Project Schedule (Daily)
  • Control Project Execution
  • Prepare Material Shipment Plan
  • Prepare Progress Report (Weekly & Monthly)
  • Analyze Problem & Prepare Corrective Action

Asst.Manager - Project controls, PT. Wiratman & Associates, Tapin Coal Terminal Project

START Date
  • Prepare Project Master Schedule
  • Tracking Project Schedule (Daily)
  • Control Project Execution
  • Prepare Material Shipment Plan
  • Prepare Progress Report (Weekly & Monthly)
  • Analyze Problem & Prepare Corrective Action

Senior Manufacturing Engineer, Western Digital, WDC Puerto Rico

START Date
END Date

Electronics Manufacturing Factory Fit-out.

Planned and executed the installation of semi-automatic production line for PCB assembly and test.

This project was 6 months in planning followed by 3 weeks on-site installation and commissioning in a previously used but empty 60,000sq.ft. factory in Puerto Rico.