Progress reporting

Project Quantity Surveyor, DHA, Bahria Town, Habib Rafiq (Pvt) Ltd. (JV Project), DHA Homes Islamabad 631/5000 Houses

START Date
END Date

Worked with Malaysian Managment team, my resposibilities were there to take off quantities of material, bar bending schedule, rate anylasis of construction items and preparing of monthly base project cost according to phisically work done.

Senior Planning Engineer, PES Arabia, On secondment to ARAMCO PROJECTS

G
Gordon Hall 👤 Member for 22 years 1 month
START Date
END Date

During my time with Aramco, I was seconded into the Community & Industrial Facilities Division.  I was site planning engineer for the construction of the Mubarraz Industrial Training Centre,the air conditioning to the centre which was a dedicated chiller plant and cooling tower constructed as part of the overall project.  My responsibilities continues on to the Mubarraz Area Maintenance Training Centre on the adjacent site, and two additional centres being constructed simultaneously by the Korean contractor in Abqaiq and Udhailiyah., I then moved on to plan the construction of

Senior Planning Engineer, Occidental Petroleum (Caledonia) Ltd, Scapa Field Subsea Template

G
Gordon Hall 👤 Member for 22 years 1 month
START Date
END Date

Plan the fabrication of the Scapa Field Subsea Template being constructed at Lewis Offshore. Approve all logic network diagrams submitted by the contractor. Integrate contractor's progress into the overall plan for the Scapa Field Development.  

Senior Planning Engineer, Brown & Root Vickers, Great Man-made River

G
Gordon Hall 👤 Member for 22 years 1 month
START Date
END Date

This project is one of the largest civil engineering projects undertaken in the world.  The concept is to take potable water from two aquifer fields in Tazerbo and Sarir, 1000km south of Ajdabiya, via a 4.3m diameter concrete pipeline from each to firstly a mixing reservoir in Ajdabiya, and from there by two separate lines, one to Benghazi and the other along the coastal plain to Sirte.  The 4.3m diameter pipeline was manufactured in 4.5m length sections, in two strategically placed plants constructed for the purpose, and shipped along dedicated haul roads constructed and maintain

Senior Planning Engineer, Wimpey Offshore, Arbroath Field Development - Montrose Alpha Mods

G
Gordon Hall 👤 Member for 22 years 1 month
START Date
END Date

Review existing schedule for Amoco Arbroath Project - Montrose Alpha Modifications Phase I.  Assess progress and re-schedule where appropriate to minimise/recover any slippage 

Senior Planning Engineer, Foster Wheeler Wood Group, Mobil 1989 Subsea Development

G
Gordon Hall 👤 Member for 22 years 1 month
START Date
END Date

Plan the detail design for the Mobil, 1989 Subsea Developments associated with the Beryl Field. Plan the conceptual and detail design for the B P Pipeline Safety Project covering all B P operated North Sea Platforms and Pipelines, plus all third party lines and platforms using B P facilities for transporting of oil and/or gas. 

Subsea Planning Engineer, Shell Exploration & Production, Osprey Project

G
Gordon Hall 👤 Member for 22 years 1 month
START Date
END Date

Responsible for the control of the programmes generated by the Subsea Mechanical, Umbilical and Controls contractors for the Osprey Project. The field was being produced by means of two subsea linear block manifolds fed by 6 individual production well-heads, serviced by 5 water injection well-heads controlled remotely via a single armour coated 7km umbilical containing 11 fluid and 4 quad electrical cores.