Project Coordinator, EC Harris International Ltd., Various Building and Civil Works Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
600
Experience Hours (Forensic Analysis)
300

Projects ($50M to $350M): The Landmark, Al Wahda City 1 Towers, Al Wahda Mall, The Central Market, Marina Mall Extension Phase II • Analyzed Primavera schedules, resource levelling, cost estimates and quality management plan for residential and commercial buildings.• Conducted site inspections and prepared Progress Reports• Participated in developing project chart

SITE ENGINEER/PROJECT COORDINATION ENGINEER/SAFETY ENGINEER, Rishabh Agro Industries Limited, Construction of Milk Plant Project

S
Sanjay Jain 👤 Member for 23 years 10 months
START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
500

Coordination, Construction and Procurement Engineer

Construction of Milk Plant Project including coordination, site supervision and procurement

Planning Manager or Senior Planning Manager, KEO INTERNATIONAL CONSULTANTS, Convention Centre, Educational Institutes EDUCATION CITY, Infra and Landscaping, Utilities Buildings

S
Sanjay Jain 👤 Member for 23 years 10 months
START Date
Experience Hours (Planning & Scheduling)
18000
Experience Hours (Cost Management)
3000
Experience Hours (Forensic Analysis)
6000

Senior Planning Manager (current)

Working as CM consultant on mega building projects  both construction and design & build. My role involves planning, scheduling, progress monitoring, reports, risk assessment, claims assessment, cost control, contractual correspondence etc

Project Manager, Principal's Representative, Advisian, Various

B
Brett Roper 👤 Member for 10 years 2 months
START Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
4000

I worked closely with client teams in a Project Management and Project Delivery capacity on many road, infrastructure, mining and resources, utilities, port, rail and building projects, including the following key projects:

Toowoomba Regional Council – NDRRA Flood Restoration Project

QR National – Rocklands to Warren Rail Duplication and Signals

DEXUS – 123 Albert Street Level 4–8 Project

Aurizon Network – Abbot Point and Hay Point – Pit to Port Review

LinkWater – Northern Pipeline Interconnector Stage 2

Senior Project Engineer / Project Manager, Lend Lease, Various

B
Brett Roper 👤 Member for 10 years 2 months
START Date
END Date
Experience Hours (Planning & Scheduling)
8000
Experience Hours (Cost Management)
4000

Responsible for the design management, planning, procurement, delivery and on-site construction management and site supervision of commercial high rise demolition, construction, and refurbishment projects throughout New South Wales, ACT, Victoria, Western Australia and most recently in Queensland.

Project Manager, Baulderstone QLD, BER Stage 2, Prince Charles Hospital Upgrade

B
Brett Roper 👤 Member for 10 years 2 months
START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
4000

Prince Charles Hospital Upgrade

As Project Manager, I managed of a team of twenty direct staff and nineteen subcontractors, ensuring the successful design, planning, procurement and delivery of Stage 2A ($18 million) and Stage 2BC ($25 million) of the redevelopment and expansion of the hospital for Project Services and Queensland Health.

Procurement, Estimator, Planning and Scheduling, Claims, Document Control, Three O Construction, Multiple Building & Civil Construction $1M to $20M

START Date
END Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
5000
Experience Hours (Forensic Analysis)
2000

Procurement Manager, Planner, Document Controls, Estimator, Claim Analysis, Company Representative at Small Business Negotiations 

Project Manager, Axion Energy, Refinery Expansion

START Date
END Date
Experience Hours (Planning & Scheduling)
450
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
0

Axion Energy                                                                                                &

Project Manager, Axion Energy, Refinery Expansion

START Date
END Date
Experience Hours (Planning & Scheduling)
450
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
0

Axion Energy                                                                                                &

Project Manager, Axion Energy, Refinery Expansion

START Date
END Date
Experience Hours (Planning & Scheduling)
450
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
0

Axion Energy                                                                                                &