Planning Development Strategist, Alstom Power Sweden, Internal PLanning Development
Devlop planning strategy including creating standardized Time Schedules suitable for all of Alstom operations.
Devlop planning strategy including creating standardized Time Schedules suitable for all of Alstom operations.
- Break down work packages to level 3 planning and scheduling. And provide final baseline for present recommendation how to best economical sequential operation at site.
- Verification the on progress schedule with the contract duration. And determine the slippage.
- Verification the physical accomplishment against BOQ content.
- Oversee overall site construction operation, Promote team work among site staff and supervisory level.
- Review Work Schedule and manpower histogram.
- Keep track of progress accomplishment, monitor procurement schedule.
Rizzani De Eccher S.PA., Qatar
- North Manama Causeway Road Access & 1.2 Km. Bridge Manama, Bahrain PROJECT - 98,000,000.00 BD {Contract Package)
- Road Construction, Underground Utilities,
- Cast-in Place Loop Fly Over
working as a planning engineer at construction company in qatar, using primavera p6 to prepare time schedule for tenders and construction programme for ongoing projects , provide weekly and monthly look ahead shedules, analyzing the planned and actual work of activities and resolve the delay in project.