Planning Engineer, AL MUNTASER TRADING AND GENERAL CONTRACTING CO.W.L.L, NEW ACID GAS REMOVAL PLANT

A
Arun Ram 👤 Member for 13 years 5 months
START Date

• Development of Base Line Schedule using Planning Software PRIMAVERA (P3 or P6)

• Project Planning using project management software Primavera & Microsoft Project(MSP)

• Preparation of Weekly, Monthly & Three Months look-ahead Schedule. Updating actual Progress and all related information & comparison analysis.

• Project report generation through Project management software

• Conduct project progress meetings in order to control & resolve critical activities.

• Review project along with project head

Assistant Planner / Engineer -Electrical, Impasse Technologies, Solar Electrification

START Date
END Date
  •  
  •  Planned and prepared schedule for renewable energy PV projects for rural estates and street lighting
  •  Established schedule logic and drew up master schedules to establish work sequence, prioritize, establish workflow and expedite operations to keep projects on track
  • Monitored and reported on activities progress, materials staging, and logistics co-ordination
  • Planned a testing schedule for

CIVIL / PLANNING ENGINEER, Komuthi Engineering Services , (various projects)

START Date
END Date
  • Preparing monthly work plan using MS Project,PrimaveraPreparing Method Statement and cash flow forecast for the tendering division,
  • Maintain the company rates data for subcontracting items and negotiate with the subcontractors for subcontracted items. 
  • Calling Progress Monitoring Meetings for all sites and circulate the minutes.
  • Represent the company in the meeting with Client, Consultants and Utility authorities.
  • Monitoring the Site Progress Financial Progress  and  prepared the Physical Progress Vs Financial
  • Progress Report to th

Assistant Engineer - Planning & Project Control, Grupo Profesional Planeacion y Proyectos, Several

START Date
END Date

 

GRUPO PROFESIONAL PLANEACION Y PROYECTOS, SA DE C.V. (April 2003 to February 2007)

Project Control Leader.

Projects:

• Engineering services for process plant projects, products and technical assistance for construction and development of user bases in the Integral Active Veracruz, Mexico

Construction Project Planner, Babcock International Group, Various Overhead Line Construction Projects

J
John Sims 👤 Member for 15 years
START Date

Working on various Overhead Line construction projects for Babcock Power as a project planner.

The majority of projects which are based in the UK including new build and refurbishment projects.

PROJECT ENGINEER, undefined, Auditorium, Skill acquisation Center

START Date
END Date

 

Position: General Supervisor

·         Supervise project to ensure strict adherence to architectural and structural design.

·         Define the scope of work

·         Work planning and control

·         Quality control

Management Trainee, Mammut Technocrete F.Z.E, Residential Project

START Date
END Date

 

Development of Micro Level Plans based on Project’s Master Schedule.

Project Scheduling & Sequencing of various activities using Primavera.

To Prepare Monthly Program/Targets for Execution of Works.

To update the progress on Weekly basis & trace out the delays.

            To Prepare Weekly & Monthly Reports, Cash Flows & Financial Progress Report.

Assistant Planning Engineer, JC Maclean Intl, Ritz Carlton Hotel, Rosewood Project, Sowwah Project

R
Rosalie C 👤 Member for 13 years 5 months
START Date

I am responsible for preparation of Interior Design Construction Schedule, Generation of Project Bar/Gant Chart regarding Project Plan Production and Manpower Resources, Prepare Pre‐Construction Planning in terms of execution on site, Prepare Weekly and Monthly Project Status Report, Prepare detailed schedule using Primavera 3 or Primavera 6 (weekly and monthly lookahead)and Inspect project site accomplishment and coordinates changes into schedule

Bid/Project Planning Engineer, QATAR -NIGERIA CONSTRUCTION DOHA, QATAR, IT INFRASTRUCTURE

START Date

 I am IT Engineer  with over 10 years post graduation experiene .However I gathered w experience in managing IT department.In the last 6 months I have been involved in IT project planning. The experience has prompted me to give project planning and broader project management a second look as a full time planner.