)Planning

Senior Planner, Naseria Contracting, 1. G+5P+Activities Floor+33 Twins Typical Floors High Rise Building Construction of Manazil Tower Five at Sharjah - UAE

START Date
END Date

 

WORK EXPERIENCE

2008-2012         Naseria Contracting Establishment – Senior Planning Engineer             UAE                                                                       

Construction Project Planner / Senior Planner, "Haif Construction Co.,Saudi arabia", 1) Infrastructure 2) Sewerage Treatment Plant 3) Bridge works 4)Building works

START Date

- Preparing Construction Schedule at Bid Submission Stage.

- Preparing Detailed  Implementation Schedule (After Contract award).

- Preparing CPA (Critical Path Analysis) & Baseline Schedules.

- Developing Manpower histogram & Other Progress Tracking, “S” curves.

- Reporting Delay & Claims.

- Dealing  with Scope changes/Variances.

Application Engineer / Planner / Primavera Application / Trainer, Consolidated Construction Consortium Limited, Planning for infrastructure projects

START Date
END Date

 

Planning Engineer 

.Analysis of tender information and review tender programmes before submission.

·Review and understand the scope of works through drawings post award of contract.

·Discuss with site team for realistic production rates and resource levels for the works being undertaken. Understand the site constraints and logistics. Discussion with all departments such as Design, M&E and sub-contractors in order to produce a fully coordinated plan.

Construction & Commissioning Engineer, Silungisa Projects, Durban 2010 Soccer World Cup Stadium

START Date
END Date

Installation of Steel Structures, Cable Structures and Membrane Roof for Pfeifer Seil und Hebbe Technik at the Moses Mabhida 2010 FIFA world cup stadium.

Erection of Tensile Structures for MTT. Site survey. Selection and qualification of sub-contractors. Site establishment, civil works, utility supply, building work, rigging, equipment installation and site acceptance.

Bid/Project Planning Engineer, Kaefer C&D, DEVELOPMENT OF SIPCHEM PLANT JUBEL

R
rizwan khan 👤 Member for 13 years 9 months
START Date
END Date

 

ØEstablish and manage effectively a planning and progress control system in order to support the Project Manager decision making process and allow him to complete the project according to the internal baselines and in compliance with the contractual dates and requirements

ØEnsure any deviation from plan is promptly spotted and analyzed, final time impact is estimated and the effect of corrective actions taken is monitored.