Creation of Work Breakdown Structures (WBS) and development of schedules

Supervising Project Controls Specialist/Project Controls Lead, WSP|Parsons Brinckerhoff, Eastlink Final Design I90 LRT project in Seattle

START Date
END Date
Experience Hours (Planning & Scheduling)
1150
Experience Hours (Cost Management)
150
Experience Hours (Forensic Analysis)
100

- .

WSP | Parsons Brinckerhoff, Seattle, WA                                           (2015)

:

This project entails modifications to 6.9 miles of the existing Interstate 90 highway – including a floating bridge and two tunnels.

 

Position Scope:

 

Senior Planning Engineer & Cost Controller, Arabian Industries LLC, ZADCO - PWT package and Al-noor, Sakia, ZALZLA, Harweel pipeline EPC work

START Date

Working as Sr. planning Engineer & cost control engineer, with 10+ years of accomplished experience in managing manufacturing and Production across Oil & Gas sector. Currently working with Arabian Industries LLC., Oman  as Sr.

EPC Lead Planner, ND Engineering, Mkomazi Expansion Project

START Date
END Date
Experience Hours (Planning & Scheduling)
4350

Assigned to the Mkomazi Pulp & Paper Mill Project(Brownfield) with the following duties:

Develop Project WBS.

Deelop Project MTS.

Create Key Date Schedule.

Create Procurement Schedule.

Create Systems Time Schedule.

Carry out CPM and EVA analysis.

Identify and Manage Interfaces.

Manage Contractor Performance and Reporting

Monthly Reports.