PCS Coordinator, DULB, Head Office

START Date

Working as PCS coordinator:

My responsibilities includes not limited to the fllowing:

Preparing requests for proposals.

Preparing Project Quality pland and Method Statement for MEP Systems.

Preapring contractual corresponce regaring claims in terms of cost and time

Preapring manpower requirements for Mechanical System based on RS means and actual site data.

Providing and preparing O& M Manuals and giving presentation on the same

Jr. Civil Engineer, initial design and estimation, Zamil Steel Industries, Pre-engineered steel structures

START Date
END Date

 

Initial Design and estimation of Pre Engineered steel structures using MBMA for Proposal purposes.

Co-ordination between Head Office (Saudi Arabia), Area Office (Lahore), Karachi Office and Client.

Senior Planning and Scheduling Engineer, Pan Arab Consulting Engineers, Central Bank of Kuwait - New Headquarters Building Project

START Date

 

Career Objective

 

Seeking a senior planning and scheduling position with a company that can benefit from my experience in the construction industry and will enable me to grow and develop.

 

Image removed.Pan Arab Consulting Engineers (in collaboration with HOK London)



Senior Planning Engineer (Kuwait Oct 2008 – Currently).

Current Duties and Responsibilities:

 

Project Coordination and Planning Engineer, Izhar Group of Companies Pvt Ltd., Carrefour Lahore Pakistan

O
Omer I 👤 Member for 14 years 8 months
START Date
END Date

 

I worked in the capacity of coordination and project planning engineer. The project was about the construction of a Two Story Hyperstar (Carrefour) Hypermarket, in Lahore. The project cost was about 15 MLN US$. My main tasks included:

·         making a schedule,

·         managing costs,

·         controlling schedule and costs

Planning Engineer / Project Coordinator, Murr Group, “Cap Sur Ville” Residential and Recreational Project, Lebanon. The project comprised 3 high-rise buildings (34 floors above ground and 2 basements each) with a height of 120 m, 18 buildings of 7 floors

START Date
END Date

Duties include ensuring that work is progressed as scheduled by identifying trends for management attention and by taking early prevention measures; reviewing the strategy of work submitted by the construction team of the various sections and adjusting the schedule to suit work constraints and open fronted areas; monitoring and reviewing the periodically project updated schedule; site coordinating between various trades and coordinating schedule variances; identifying delay and slippage, and providing recommendations for performance improvement and/or corrective

Section Engineer - External Works, Consolidated Contractors Company CCC / HOCHTIEF (JV), Rafic Hariri/Beirut International Airport Rehabilitation and Extension

START Date
END Date

Duties include preparing reinforced concrete shop drawings and the related bar bending schedules; designing pre-cast elements for terminal buildings and got Dar Al-Handasah approval; supervising concrete works in Utility Tunnel, Terminal Building New Elevated Arrival/Departure Bridge, infrastructure works related to electrical airfield lighting for the new East and West Runways with their taxiways; supervising turnkey construction of two electrical substations and concertina fencing on top of Boundary Walls; handing over the Elevated Water Tank, Civil Aviation P

Assistant Project Manager / Project Planner, COWI Management, Borealis C1

START Date
END Date

25 years experience from projects within Energy, Process and Shipping industry in roles like planner, project manager or coordination of design work. Approx 15 years experience as manager of consultant groups 

Loop Check Coordinator, JGC Singapore Pte , Dung Quat Refinery

START Date
END Date

Contracted as Loop Check Co-ordinator on Petrovietnam's Dung Quat Refinery project. Implemented processes for the management of Project Issues and Actions using a web-based database tool. Role as Loop Check Co-ordinator involved liaison between management teams of 5 zones in Project site. Implemented a deliverables tracking system for Loops, Devices, Plant Systems and Plant Areas.

Project Interface Coordinator, OKLNG (Shell, BG, Chevron, NNPC), OKLNG Development Project

START Date
END Date

Implemented processes for the management of Project Issues and Actions using a web-based database tool. Role as Interface Co-ordinator involved liaison in a Project Assurance capacity with all project departments. Organised a steering committee to commission the implementation of an integrated Business/Project Monitoring system. Interfacing with existing systems: Documentum, Q-pulse, Pertmaster. Implemented a functional analysis of the Projects Deliverables profile. Implemented an Issues and Actions Monitoring database.