Project Control Group Leader, ICA Fluor Daniel, El Boleo
Development and management of the EPC Schedule of copper, cobalt, zinc, manganese mining project. 5000 activities were scheduled to achieve the project scope. Project budget: 1,880 MMUSD
Collaboration in the development and management of EPC schedule of nitrogen generation plant project. The activity network built consisted of 1500 activities