%100 Project Planning; Cost control; Budgeting; Performance Monitoring; Project Control; Primavera P6

ANALYST / PLANNING ENGINEER, system construct, Mirdiff Commercial Development

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
1900
Experience Hours (Forensic Analysis)
1800

Worked as a project planner for various projects in Dubai

 

The responsibilities include but not limited to

  • Track the progress of works
  • preperation of daily activity report, monthly activity report
  • preperation of 3 weeks look ahead and two months look ahead programms
  • Preperation of contractual letters
  • MIS

 

Projects Handled:

  • Mirdiff central park
  • Sales centre building, Sama dubai, Jumeriah

Cost Controller, SAMSUNG ENGINEERING CO LTD, Hydro Carbon Upstreem Production Plant

START Date
END Date
Experience Hours (Planning & Scheduling)
400
Experience Hours (Cost Management)
600
Experience Hours (Forensic Analysis)
150

Working on West Qurna Phase 2 Project for LukOil Client near Basra, Iraq

 

Building Construction, STFA Construction Group, Small Boat Harbor with KOC

START Date
END Date
Experience Hours (Planning & Scheduling)
40000
Experience Hours (Cost Management)
40000
Experience Hours (Forensic Analysis)
40000

Assigned as a Deputy Project Director by STFA since they are in JV with CANAr Contracting Co. Appointed to resolve the problems the job site was facing and managed the progress of the Civil, electromechanical and finsihing works. Also managed good relashionship with the Owner and the Consultant. Got the job moving with a substantial progress and participated in the Contractual related issues on site.

Engineer, Planning and Project Control, MMC Oil & Gas Sdn Bhd, Platform

START Date
END Date
Experience Hours (Planning & Scheduling)
950
Experience Hours (Cost Management)
200

Planning & Project Control Engineer for local engineering consultant focusing on planning & scheduling activities including:

Project Planner, Balfour Beatty Rail, Balfour Beatty Rail ROMANIA, Rehabilitation of the railway Pan-European 4th Corridor, Client: CFR S.A. Romania

START Date
END Date
Experience Hours (Planning & Scheduling)
1050
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
50

Project Planner, Balfour Beatty Rail

Project: Rehabilitation of the railway Pan-European 4th Corridor, Client: CFR S.A. Romania

Assistant Manager - Project Controls, LLC, Virginia Indonesia CO., Drilling Location Construction Service

E
eko setiadi 👤 Member for 11 years 6 months
START Date
END Date
Experience Hours (Planning & Scheduling)
250
Experience Hours (Cost Management)
250
Experience Hours (Forensic Analysis)
250

Drilling Location Construction Service CBM for Virginia Indonesia CO., LLC, Muara Badak

Establish drilling location construction of Coal Bed Methane and conventional reservoirs for VICO