I am an architectural engineer. I have worked in Architecture design offices and currently working as planning engineer on a residential colony project. I have 2 years of design and site work experience and 1 year planning experience.

On design project i have designed residential,commercial projects and along with design worked on site for the implementation as per specfication.I have been using Autocad and 3d max for past 5 years.Gain some handy experience on 3d rendering.

Project Scheduler, URS Infrastructure & Environment UK Limited, UCH II Expansion Project (404 MW-Combined Cycle Power Plant)

START Date

 

I am involve in the following responsibility during this project

§  Monitor the project schedule on Primavera P6 and project progress against the EPC Contractor’s construction and commissioning schedule and assist the EPC Contractor’s planning and interfacing activities to limit the impact of any programme deviations.

§  Assist the Owner in all aspects of site supervision of EPC Contractors (Hyundai and Descon)

Amjad Gul

A
Amjad Gul 👤 Member for 13 years 2 months
First Name
Amjad
Last Name
Gul
Professional Since
Oldest experience
Years Experience
43
Telephone Number
0097470307980
LinkedIn Profile
www.linkedin.com/Amjad Khan Bangash

 

·     Ability to perform multitasks with lots of interruptions and to include prioritization.

·     Taking basic instructions and then quickly grasp the tasks to produce the desired result.

·     Excellent in Software & Hardware installation and Trouble-shooting.

fakhar abbas

First Name
fakhar
Last Name
abbas
Professional Since
Oldest experience
Years Experience
43
Telephone Number
+923085101649
Facebook Profile
http://www.facebook.com/fakhar.abbas.73157

Planning Manager, Ansaldo Energia spa, Liberty Power Project 223 MW Combined Cycle

START Date
END Date

Managing project planning team to streamline schedule and progress reporting from main contractors. Liasing with Site manger in matters of contract/contractor management. Varifying/auditing reported progress.