Pakistan (AS.PK)

PK

Farhan Ahmed Memon

First Name
Farhan Ahmed
Last Name
Memon
Professional Since
Oldest experience
Years Experience
51
Telephone Number
+971543791327
LinkedIn Profile
www.linkedin.com/in/farhan-ahmed-b2aa62121
Twitter Profile
N/A

 

There are some skills as listed bellow, 

1. Project Planning,

2. Scheduling,

3. Control,

4. Cost Control,

Planning Engineer, Pipelink Construction Private Limited (PCL), 1132/ KPD PC-1 installation/Supply of flow lines & Gas gathering Facility.,Sawan North Horizontal-1 Well head Development project – Installation of Well Head Cooler Control/Solar Panel, Sou

START Date
END Date
Experience Hours (Planning & Scheduling)
8550
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50
  1. Develop, review and maintain the project plans and baseline schedules using Primavera
  2. Monitor progress throughout the construction process on a weekly basis and compare with work plan (Actual vs Baseline Schedule)
  3. Identify and review regularly, critical and sub-critical activities and monitor its impact on overall plan
  4. Develop and maintain project change control and review scope change requests for impact on schedules and the critical path of the project.
  5. Submitting planning package with all allied documents
  6. Ensuring availability of drawings in l

Area Planning Engineer, ORIENT Energy System (Pvt.) Limited (OES), Construction of THATTA POWER PLANT, DADU POWER PLANT, OMNI POWER PLANT

START Date
END Date
Experience Hours (Planning & Scheduling)
4900
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50
  1. Develop, review and maintain the project plans and baseline schedules using Primavera
  2. Monitor progress throughout the construction process on a weekly basis and compare with work plan (Actual vs Baseline Schedule)
  3. Identify and review regularly, critical and sub-critical activities and monitor its impact on overall plan
  4. Develop and maintain project change control and review scope change requests for impact on schedules and the critical path of the project.
  5. Submitting planning package with all allied documents
  6. Ensuring availability of drawings in l

ASAD LATIF

A
ASAD LATIF 👤 Member for 8 years 3 months
First Name
ASAD
Last Name
LATIF
Professional Since
Oldest experience
Years Experience
3
Telephone Number
00923456020093
LinkedIn Profile
ASAD LATIF FARIDI
Facebook Profile
ASAD LATIF

Assistant Planning Engineer planning construction, Descon Engineering Limited Pakistan, shutdown Parco Refinery

A
ASAD LATIF 👤 Member for 8 years 3 months
START Date
END Date

Study, review and fully understand job content and work scopes within the area. 2. Prepare, review and verify Job packages 3. Perform Job walk / site verification to ensure job packages are fully complete and satisfactory. 4. Identify/review requires material 5. Identify resource and equipment requirement 6. Identify critical path for the area 7. Plan and lead his specific area team to meet the target set. 8. To create the contingency plan for critical equipment. 9. To ensure all the task in his area are scheduled properly. 10.

Planning Engineer planning construction, Doha Petroleum Construction Company, Oil and Gas Projects: Facilities

A
ASAD LATIF 👤 Member for 8 years 3 months
START Date
END Date

Study, review and fully understanding job content and work scopes within the area. 2. Prepare, review and verify Job packages 3. Perform Job walk / site verification to ensure job packages are fully complete and satisfactory. 4. Identify/review requires material 5. Identify resource and equipment requirement 6. Identify critical path for the area 7. Plan and lead his specific area team to meet the target set. 8. To create the contingency plan for critical equipment. 9. To ensure all the task in his area are scheduled properly. 10.