• Construction of Stilt + 18 Floors Residential Tower at Lower Parel, Mumbai.
• Development of basic project statement into a fully detailed precedence network using Primavera.
• Responsible for preparing the Project Master Schedule, and coordination with the Client for approval.
• Setting up the detailed progress monitoring system. Design and implement reporting formats for various departments.
• Preparation of medium and short-term programs (3 Week Look ahead), in close liaison with the Project Manager.