Planning Engineer-Mechanical, TATA Consulting Engineers Limited, Power, Industrial, Oil and Refinary

START Date
END Date

·         Coordination with execution team to ensure timely & cost effective implementation of Project.

·         Review of contractor’s schedules and monthly reports (MPR) and providing detailed comments.

·         Preparation of MIS Reports along with Progress Curves for Management

Planning Engineer-Mechanical, TATA Consulting Engineers Limited, Power, Industrial, Oil and Refinary

START Date
END Date

·         Coordination with execution team to ensure timely & cost effective implementation of Project.

·         Review of contractor’s schedules and monthly reports (MPR) and providing detailed comments.

·         Preparation of MIS Reports along with Progress Curves for Management

kaushik mohanty

First Name
kaushik
Last Name
mohanty
Professional Since
Oldest experience
Years Experience
5
Telephone Number
0919930142967

 
  I am Kaushik Mohanty
 
I have done My Post graduation in construction management from National institute of advance construction management and re

PLANNING HEAD MONORAIL PROJECT, SCOMI ENGINEERING , MUMBAI & KUALA LUMPUR MONORAIL

START Date

I have done my post graduation in Advance construction managenment from affiliated university in India.

I have my experince as a Porject planning personnel at Dubai Metro rail project & Mumbai metro rail project.

I was responssible for overall project planning for E&M work & Civil constrcution work.

PLANNING HEAD MONORAIL PROJECT, SCOMI ENGINEERING , MUMBAI & KUALA LUMPUR MONORAIL

START Date

I have done my post graduation in Advance construction managenment from affiliated university in India.

I have my experince as a Porject planning personnel at Dubai Metro rail project & Mumbai metro rail project.

I was responssible for overall project planning for E&M work & Civil constrcution work.

Bid/Project Planning Engineer, Abir Infrastructure Pvt. Ltd., 1750 MW Demwe Lower Hydro Electric Project, India

START Date
END Date
  • Project Planning and Schedule for a Hydro electric Project 
  • Constructional Power Planning & Costing 
  • Planning of the communication systems for a remote location 
  • Planning of the automation of the work and a centralized sub station to monitor the resources(equipment, vehicles, manpower, stores etc.,). 
  • Insurance claims 
  • Project monitoring for a transmission line 
  • Planning of the equipment in respect to power generation and the related equipments along with their automation. 
  • Conveying systems

Bid/Project Planning Engineer, Abir Infrastructure Pvt. Ltd., 1750 MW Demwe Lower Hydro Electric Project, India

START Date
END Date
  • Project Planning and Schedule for a Hydro electric Project 
  • Constructional Power Planning & Costing 
  • Planning of the communication systems for a remote location 
  • Planning of the automation of the work and a centralized sub station to monitor the resources(equipment, vehicles, manpower, stores etc.,). 
  • Insurance claims 
  • Project monitoring for a transmission line 
  • Planning of the equipment in respect to power generation and the related equipments along with their automation. 
  • Conveying systems