Australia (OC.AU)

AU

Construction Site Planning, BECHTEL, Comalco Special Projects Misc.

M
Mark Smith 👤 Member for 20 years 6 months
START Date
END Date

Building and developing new and maintaining the existing construction schedules for the current 66 Special Projects for increase and maximisation of plant production.

  • Working in a management team maintaining the schedule requirements of 8 x Site Project Managers.
  • Daily client and contractor interface and schedule review during routine construction and shutdowns.
  • Contribution to weekly and monthly data collection and reporting including forecasts and trends.
  • Taking weekly progress photos, editing and issuance thereof a

Construction Site Planning, BECHTEL, Yarwun 2 Alumina Refinery Expansion Project

M
Mark Smith 👤 Member for 20 years 6 months
START Date
END Date

Building and development of the Bechtel Construction pre-bid Proposal and resourced Construction Execution Schedule with approximately 1,376,583 manhours within a team of planners.

  • After handing over the developed Bechtel Construction schedule to a dedicated contract scheduler for that seperable portion of work scope I resumed my role and duties as Site Project Planner within the EPCM management team for the overall Project Schedule as Principal Contractor.
  • Managing half the awarded Major Contractor Schedules and liaison within EPCM Team

Senior Planner, BECHTEL, Queensland Curtis LNG Project

M
Mark Smith 👤 Member for 20 years 6 months
START Date
END Date

Development of Cost Control and Contractor reporting systems until project gained NTP.

  • As I was deployed to the site very early ahead of the LNG Tanks’ commencement I assumed roles of both cost and trends engineer in the field reporting back to Bechtel corporate in Houston, Texas.
  • Job function included tailoring subcontractor reporting formats and monitoring early works subcontractors for marine facilities, site preparation (including clearing and bulk earthworks), camp facilities and Bechtel internal direct hire scope.
  • For the

Simon Hoadley

First Name
Simon
Last Name
Hoadley
Years Experience
0

Been in the Project Controls arena since my first serious under graduate job - mining company expansion project. Have been:

Planner

Project Controls

Cost engineer

Estimator

 

Kenneth Rodrigues

First Name
Kenneth
Last Name
Rodrigues
Years Experience
0

Live in Melbourne,Australia, worked in System Test Engineering in Semiconcudctor industry, Telecommunications ( Mobile Radio,Telepower ), Resources and now Defence Industry. Like Mt biking ,Camping in Summer, Cross-country Skiing in Winter. Familiar with Unix BSD , Windows 3.1 to 7.0, MOSPL II , MOST XE and Project management software ( MS Project, Primavera P3, Timeline) and OPP 3.1 

Claims Management, Evans & Peck, Darwin Ports Authority Ship Loader Project and Various Projects

START Date
END Date

Procurement for multi-million infrastructure project in Sydney. Assessment of Extension of Time Claims in $500M Rail Construction Project. Assistance in Expert Report for Arbitration. Assistance in Expert Delay Analysis Report for Expert Determination Review of Extension of Time claim for the Government of the Northern Territory. Review of Variation Claims made on a major Ministry of Defence project. Review of EOT Claim of SoPA Adjudication in NSW.

Richard Croxson

First Name
Richard
Last Name
Croxson
Professional Since
Oldest experience
Years Experience
41
Guild Accreditation
Awaiting Applicant
Telephone Number
+61 447 607507
LinkedIn Profile
http://www.linkedin.com/pub/richard-croxson/b/719/48a

richard_croxson.png

Richard is a chartered quantity surveyor and barrister* with twenty years experience in the construction industry. He has provided commercial and dispute advice for employers and contractors as well as preparing and defending claims for extensions of time, disruption and prolongation for domestic and international arbitration. He has also prepared contracts for major construction projects and has experience in building, ship building, civil, heavy engineering, power, rail, water, oil and gas works.

Lola Adu

L
Lola Adu 👤 Member for 14 years 6 months
First Name
Lola
Last Name
Adu
Oldest experience
Years Experience
41

I have been doing and cad do:

  • Project engineering
  • Project Planning
  • project scheduling
  • planning report
  • claim analysis
  • cost controls
  • EVM analysis
  • Project controls
  • contract admin
  • Risk management
  • construction management
  • Project management
  • Study management
  • Program management