Planning Engineer, Abdulali Alajmi Co., Infrastructure Project of Industrial City Development
Worked at Head Office : Dealt with Preliminary Plans & Master Shceduler.
Working at site : Schedule Updates & Progess Reporting
SA
Worked at Head Office : Dealt with Preliminary Plans & Master Shceduler.
Working at site : Schedule Updates & Progess Reporting
Senior management professional with 19+ years of diversified and progressive engineering experience including Project Management, Project Controls, Planning, Cost control, risk management, change management, Cost Estimation, Design and Site supervision. Currently functioning as Project Controls Manager with Saudi Arabian Construction Company (SACC).
- Extensive experience working in PMO and controlling mega projects within the Construction field
Involved in designing of steel structures such as shopping malls, accommodation & office buildings, showrooms, aircraft hangars, sports facilities, warehouses, etc based on latest international codes and standards (UBC, IBC, MBMA, ASCE, ANSI, AISC, LRFD, BS, AISI) using several software to produce optimized designs using 3D and composite design
Spearhead operations of the Project Controls Department encompassing activities like planning, scheduling, cost control, risk management, cash flow, budgeting and reporting across multiple large projects (valued SAR 3+ Billion) for Aramco and TOTAL
- Project Controls Manager in PMO in charge of SAR 4.2 Billion MOI Housing Project including 3 sites with 2700 units.
· Thorough and proficient in 16 Division Master Format of Construction Specifications Institute (CSI)
· Contractor Method of Measurement (MOM) responsiveness
· Detailed Take offs from working drawing
· Set up for Bill of Quantities or Materials (BOQ/BOM)
· Set up Cost Price Breakdown
· Preparing a tender and contract documents, including bill of quantities BOQ
· Undertaking detailed take offs in the format to be use within interim or payment applications and Variations
· Prepared the materials schedule for approval and request for quotation (RFQ).
· Monitored all materials requested are received and follow up ahead the others to avoid delays.
· Undertake detailed take offs in the format prescribed by the Project method of measurement (MOM) to be use within interim or monthly payment applications and Variations.
· Prepared the materials schedule for approval and request for quotation (RFQ).
· Undertake preparation of payment certificate
· Prepared detailed takeoffs from division 2 to division 13.
· Advised and coordinate the procurement Engineer on procurement strategy.
· Prepared a cost price breakdown for a new works not included in the BOQ.
· Revised cost price breakdown for potential savings.
· Analyzed bid drawing with approval or IFC drawing for cost comparison and for potential savings.
· Prepared detailed takeoffs from division 2 to division 13.
· Prepared the materials schedule for approval and request for quotation (RFQ).
· Prepared a cost price breakdown for a new works not included in the BOQ.