Core senior Planner, AL GEEMI & PARTNERS CONT. CO. L.L.C, HEAD OFFICE

START Date
END Date

MyJob: Senior Planning Engineer

location: Abu Dhabi, UAE

Company: Al Geemi & Partners Contracting Co. L.L.C.

 

Job Description:

2008 - to Present , UAE, Senior Planner - Tender Planning for various projects: Road infrastructure and utilities, building construction, Mechanical facilities, air-base pavements and utilities, by AL Geemi & Partners.

2004-2008, KSA, Project Controller - Prepare planning, cost control, for project executions: Road infrastructure, Reinforced concrete bridges, by UNIMAC.

Core senior Planner, AL GEEMI & PARTNERS CONT. CO. L.L.C, HEAD OFFICE

START Date
END Date

MyJob: Senior Planning Engineer

location: Abu Dhabi, UAE

Company: Al Geemi & Partners Contracting Co. L.L.C.

 

Job Description:

2008 - to Present , UAE, Senior Planner - Tender Planning for various projects: Road infrastructure and utilities, building construction, Mechanical facilities, air-base pavements and utilities, by AL Geemi & Partners.

2004-2008, KSA, Project Controller - Prepare planning, cost control, for project executions: Road infrastructure, Reinforced concrete bridges, by UNIMAC.

Assistant / Planning Engineer, Galfar Engineering & Contracting SAOG,Oman, Port Hedland Inner Harbour Project

START Date

 Job Responsibility:
1) To Plan project cost, resources required, duration of project( Budget ,yearly Budget)
2) To track the project and submit monthly planned Vrs Actual Report.
3) To submit Monthly Progress Report to client with records like (Site dairy ,RFI& Photos)
4) To ensure business plan by BMR (Business Monthly Review)
5) To make Schedule of project & Organization chart with demobilizing dates
6) To monitor the project by making ABPS (Activity Based planning Schedule)
7) To track materials submittal, approvals & consumption.

Assistant / Planning Engineer, Galfar Engineering & Contracting SAOG,Oman, Port Hedland Inner Harbour Project

START Date

§  Current employment   

Ø  Organization: Galfar Engineering & Contracting  SAOG, Oman

Ø  Project:1) Construction of fishery Harbour and buildings, Barka

               2) Construction of new jetty, wudam        

Project Planner, Hill International (Oman), Airports

START Date
END Date

Muscat Phase 1 & 1A and Salalah Phase 1 - Various Critical Facilities required by Client for operational use (i.e. Air Traffic Control Tower, Air Traffic Management Building, Sea Rescue Station, Contingency & Training Center, New Ruway, Airfield Lighting Systems, Air Traffic Management Systems, Instrument Landing Systems, Data Centers, Utility Suppor facilities).

SNC09 Package - Air Traffic Management Systems

SNC10 Package - Navigation Aids Systems