Iran (AS.IR)

IR

Project Planning and Control Specialist, ASRE MODIRIAT BINA Consulting Company, Strategic planning for GERAD Company

START Date
END Date
  • as Project planning, controlling and systems developing full time Engineer in ASRE MODIRIAT BINA Co.

Company name & location: Asre Modiriat Bina Co. – Tehran – Iran

Asre Modiriat Bina is management consulting in strategic management, System and Process management, Project management and Human resources management fields.

Website/Email: www.binamanagement.com

Planning and Balance Engineer, Avec, Iran Khodro Montage Line2

START Date
END Date

Planning, time measurement & balance of Iran Khodro Montage Line2 Iraniancar manufacturing Company (Tehran-Iran), as a member of a 20 people team we increased the productivity from 26 to 34 cars per hour, Used Stopwatch & Basic Most methods for time measurement & simulate the new Line for Balance of old Line to approach the best production planning program.

Planning and Project Control Chief Engineer, OIEC, South Pars Gas Field Development Phases 9&10

START Date
END Date

Project 2:  South Pars Gas Field Development Phases 9&10 (2800 million USD project)

Title:     Planning & Project Controls Chief Engineer (At Site) (Sep 2003 to Dec 2005)

Farangis Kavian

First Name
Farangis
Last Name
Kavian
Professional Since
Years Experience
0
Telephone Number
00989132706525

Professional Experience

In Planning & Scheduling

-Carrying out system tasks within agreed timescales and budgets and reporting system status and deviations to the project manager.

-Provision of Planning & WBS

-Prepare programmer of works, labor chart and cash flow

-Projected Cash flow (S-Curve)

-Define technical responsibilities within the project - interfaces, system and work packages.

Mohammad kanani

First Name
Mohammad
Last Name
kanani
Professional Since
Years Experience
0

I have MSc degree on the field of Industrial Engineering. I'm very intrested in Programming,Information Systems and Project Management knowledge and its related tools and techniques and also I'm a Project planning and controlling expert in a shipbuilding company. I'm working with Pm softwares like Oracle Primavera P6v7, Microsoft Project 2010,Oracle Primavera Risk Analysis and ms Excel 2010 and database MS like MS Access 2010 and MS SQL Server 2005.

Head Planner & Controller, MAPNA, Yazd Solar Thermal Power Plant (2x159MW Gas, 1*132MW Steam, 17MW Solar)

START Date
END Date

 

                      ·   Execution Strategy

                      ·   Level 2 time schedule

Head Planner & Controller, MAPNA, NEKA Combined Cycle Power Plant (1x160MW)

START Date
END Date

 

                      ·   Execution Strategy

                      ·   WBS (Basic & Detail Design, Tendering, Supply/Manufacturing, Transportation, Civil, Erection & Commissioning)