Wood Group Planner

Responsible for all planning related activities for initially, the Hummingbird FPSO, from fit out in Rotterdam shipyard during construction to Sailaway, Hookup, Commissioning and eventually into production.

Once the Hummingbird platform was completed I then moved on to the Voyageur FPSO project and carried out the same planning work for that project, again from Rotterdam to anchoring in the North Sea. The planning tool used was MS Project and Maximo for maintenace.

Consultant / Contractor - Self Employed Senior Planner

Working for Elf Enterprise Oil plc as Senior planner for the Claymore platform. Working in the Field operations department supervising a planner and a technical assistant. Work included maintenace, construction, production, safety, drilling and subsea work scopes. Production of detailed plans for all disciplines for major maintenance and engineering / construction work faces. The planning package utilised was Surtrak