7

I am a Chartered Civil Engineering Surveyor and member of the Chartered Institution of Civil Engineering Surveyors. I have nearly 7 years post-graduation experience across Building, Rail, Water and Aviation working within London and South East England. 

I have predominately worked in Rail and have been involved in the delivery of both London Bridge Station Development and Crossrail Farringdon Station. I have spent 2 years in water and operated as commercial lead for an outfall scheme on the Thames Water AMP6 Framework worth £6m. 

Assistance Planner, Higgins Construction Plc, science laboratory building

START Date
END Date
Experience Hours (Planning & Scheduling)
5150

Higgins – Assistant Planner

 

Higgins were constructing a science lab for a school in London worth circa £8m (P6). I was offered a role with training to develop my previous planning experience.

 

Role and responsibilities included;

Al Malick

A
Al Malick 👤 Member for 23 years 9 months
First Name
Al
Last Name
Malick
Professional Since
Oldest experience
Years Experience
17
Telephone Number
07903194006

Assistant Quantity Surveyor, Elliott Thomas, St Pauls Boys School - Drama Centre

START Date
END Date
  • Assisting with the review of all applications for payment with the site team.
  • Responsible for issuing of payment notices to reflect the work completed on site.
  • Ownership of all commercial issues on site and report to senior QS located off site with a schedule of information and an estimated cost for potential impact to the project.
  • Assist in the preparation of the monthly valuations to the client for payment and review with cost consultant EC Harris before formal submittal.

Assistant Quantity Surveyor, Bam Nuttall Limited, Crossrail Farringdon - C435

START Date
END Date
  • Assessment of subcontractor application for payment each period to align with the Crossrail accountancy dates for approval of the senior QS.
  • Production of 3 monthly forecast incorporating subcontract, labour, plant and materials, to be reported into project controls. Assist project controls with presentation of forecast to Crossrail programme engineer and to re-base line the section programme.
  • Collation of all labour and materials on site for reconciliation and costing as part of the monthly forecasts for the Preliminaries section.

Quantity Surveyor, Morgan Sindall Infrastructure, Q6+1 Landside Roads Renewals

START Date
  • Quantity surveyor leading all commercial project duties for 4 schemes and reporting directly into a Commercial Manager.
  • Project cost forecasting including production of Cost Value Reconciliation (CVR) and Forecasting to complete (FTC).
  • Submission of FTC to the client and review of changes in the period.
  • Payment applications to the client for the assessment of the cost and or value of direct staff, plant, materials and subcontracted works executed within each period.
  • Contract administration of all subcontractors operating under NEC3 ECS contract pricing o

Change Manager, Costain, Thameslink - London Bridge Station Redevelopment

START Date
END Date
  • Enforcement of the Network Rail project change management process which produces actual forecast cost (AFC) and actual forecast value (AFV) reports.
  • Review and approval of budget and cost movements between subcontractors, Network Rail and Costain, to ensure the transaction is auditable and contractually valid.
  • Implementation of correct use of the online change management tool (“Salesforce”) through training sessions and presentations to the project commercial team.