Romania (EU.RO)

RO

Assistance Planner, SNC - Candu Energy Inc., SFPA

START Date

- Establish Scope of Work and Delivery Schedule in Primavera plan for project (qualification / tender / execution) - Setup of WBS in Primavera (and responsible for alignment) - Maintain updated schedule with latest approved scope of work - Schedule analysis, identifying Critical Path, delivery issues and communicate to Project Manager, Engineers, procurement & construction and Client - Assist project manager in setting up Project time management plan - Produce Monthly progress reports and reporting progress to Client

Assistance Planner, SNC - Candu Energy Inc., SFPA

START Date

- Establish Scope of Work and Delivery Schedule in Primavera plan for project (qualification / tender / execution) - Setup of WBS in Primavera (and responsible for alignment) - Maintain updated schedule with latest approved scope of work - Schedule analysis, identifying Critical Path, delivery issues and communicate to Project Manager, Engineers, procurement & construction and Client - Assist project manager in setting up Project time management plan - Produce Monthly progress reports and reporting progress to Client

Assistance Planner, SNC - Candu Energy Inc., SFPA

START Date

- Establish Scope of Work and Delivery Schedule in Primavera plan for project (qualification / tender / execution)

- Setup of WBS in Primavera (and responsible for alignment)

- Maintain updated schedule with latest approved scope of work

- Schedule analysis, identifying Critical Path, delivery issues and communicate to Project Manager, Engineers, procurement & construction and Client

- Assist project manager in setting up Project time management plan

- Produce Monthly progress reports and reporting progress to Client

Project Planner, Continental Wind Project Management, Fantanele - Cogealac - Gradina Wind Farm

START Date

Creating / improving the Master Plan by including for each: permitting works, civil works, electrical works, installation works, commissioning works, TN51 and Yellow Fidic - different programmes linked in between (mpp.)
Creating programmes for weekly and monthly reports (mpp.)
Creating progress reports (mpp.)
Checking all programmes issued by the Contractor (mpp.);
Forecast development (mpp.,xls)
Earned Value Analysis (mpp.,xls)
Tracking the effective progress on site
Establishing the contractual deadlines using Yellow Fidic contract (mpp.,xls)
Establishing the strategies and improveme