Project Control Consultant, AMCG, Intel FAB 24 Ireland
· Scheduling of large scale project and Risk management
· Development and implementation of new schedule management methods
Definition and implementation of new work processes with other teams
IE
· Scheduling of large scale project and Risk management
· Development and implementation of new schedule management methods
Definition and implementation of new work processes with other teams
Alan is an experienced Project Controls professional with particular focus on planning with many years’ experience working in the Pharmaceutical Industry, both Chemical API and Biologics (drug substance and drug product), Micro-Processing and Oil and Gas Industries He has specialised in the coordination of complex ‘system based’ projects, which require high levels of interactive planning, involving wide stakeholder groups. All scheduling projects were completed using the most recent versions of Primavera or MS Project software.
I have more than 7 years extensive experience in construction phase of Gas and Oil onshore EPC projects as a project planner and controller and more than 4 years as a senior and site lead planner & project control engineer. And now I`m working in an engineering consultant company as a senior project planning engineer in Dublin on a tender programme of a rail project.
I`m fluent in Primavera P-6 and MS project, PMP (Project Management Professional) certified, Diploma certified in project management courses and PMI member.
• Master Schedules and Tender Programme for Luas Cross City Project (LCC)
• Follow project procedures and maintain them in the programme
• Prepare and present the overall cost and cash flow of the project
•Preparing Project forecast Estimation base on the BOQ
Qualified Quantity Surveyor
17 years working with Mechanical & Electrical contractors
Fields worked in
Oil & Gas
Pharmaceuticals
Bio Pharma
Data Centre
Food industry
Most experience has been gained in the Pharmaceutical & Bio Pharma industry
Planning & scheduling for about 15 years using P3.1, P6, Asta & MS Project
Alan is an experienced Project Controls professional with particular focus on planning with many years’ experience working in the Pharmaceutical Industry, both Chemical API and Biologics (drug substance and drug product) and Micro-Processing Industry. He has specialised in the coordination of complex ‘system based’ projects, which require high levels of interactive planning, involving wide stakeholder groups. All scheduling projects were completed using the most recent versions of Primavera or MS Project software.
Dublin Port Tunnel - Planning Engineer / Manager
The Dublin Port Tunnel is a major element in a multifaceted plan to tackle the transportation problems in Dublin City. Its primary purpose is to provide a high quality access route to Dublin Port, as well as relieving congestion in many areas of the city. The Project value was € 455m and comprises approximately 5.6 km of dual carriageway, which includes 2.1 km of twin cut & cover tunnels and 2.4 km of twin bored tunnels, with associated interchanges and infrastructure.