John Brown Senior Planner
CAPROLACTAM COMPLEX UPGRADE
DE
CAPROLACTAM COMPLEX UPGRADE
PHENOL REVAMP
CHLORINE / CAUSTIC REVAMP
Responsible for the PMC supervision of on-site planning and scheduling of the Chlorine / Caustic Revamp Shutdown. The scope of work consisted of the removal and reinstallation of pipework, equipment, steelwork and foundations. The areas involved were a Cell Building, Chlorine Area, Caustic Area, Brine Area, Hydrogen Area and several MCC’s Produced all management graphics and progress reports. All work to be carried out in a two-month shutdown period. Attended weekly progress meetings with the construction team
CRACKER REVAMP
Responsible for the on-site planning and scheduling of various scopes of work for a six week shutdown for the Cracker Revamp. The scopes consisted of the removal and reinstallation of furnaces, pipework, equipment, steelwork, foundations, electrical and instrumentation. Produced management graphics and progress reports.
1999
Dow BSL Bôhlen
Field Expeditor
Joining the Dow-PDM advisory team at the ethylene cracker turnaround.
Duties: with consideration to the projects mandatory dates, to visit external suppliers and workshops in order to assure earliest availability of goods on behalf of owner and its contractors.
Location: Bôhlen, Germany
Procurement by Otec B.V., Rotterdam.
Current Role
Current Role
Primavera Planning, scheduling, Progresse report , earned values analysis, bcws, acwp, bcwp