Turkey (AS.TR)

TR

Technical Office Engineer, Planning, Cost Control, Atilla İnş. Tur. ve Tic. A.Ş., Multiple (9) Projects, Ankara, Turkey

G
Gün Göksu 👤 Member for 21 years 2 months
START Date
END Date

Technical Office. Infrastructure work monthly due reports(İller Bank), Biding Dossiers, Price Assessments.

Project details:Works consisting of the construction of the foul water and rainwater systems for various small cities.

●      Monthly due reports for various construction sites (nine sites at peak, minimum 5 sites).

●      Follow-up (seek approval) on location of two site due reports with client.

Technical Office Manager, ÇEL-AT Joint Venture, Burkan-4, Bursa, Turkey

G
Gün Göksu 👤 Member for 21 years 2 months
START Date
END Date

Technical Office. Payment Certificates of client and subcontractors, Price Assessments, Cost Control.

Project details:Scope contract value US$4,000,000. Works consisting of the construction of the foul water and rainwater system for sections of the Bursa city.

●      Due reports to client and subcontractors,

●      Draftsman for company letters to be sent to client.

Technical Office Engineer, Planning & Cost Control, Alsim Alarko, Baku-Tiblisi-Ceyhan Crude Oil Pipeline, Erzincan, Turkey

G
Gün Göksu 👤 Member for 21 years 2 months
START Date
END Date

Technical Office. Planning, payment certificates of client and subcontractors, cost control (6 months).

Project details:Project value US$4Billion, scope contract value US$30,000,000. Scope pipeline total length is 387(470)km and is of 42’’ steel pipes.

●      Company master Primavera scheduler.

●      Progress reporting.

Bid/Project Planning Engineer, Kolin Construction, (Cost & Planning Tasks) Many Hotels - Industrial plants - International airports

G
Gün Göksu 👤 Member for 21 years 2 months
START Date
END Date

Kolin Construction Headquarters

Temporary assignment pending new construction project; worked for the bidding team. Prepared the schedules & methodologies for a bid. Later commissioned to write a program in excel to use in the bidding of the US embassy compounds construction works. Gained experience in bidding works and had the opportunity to learn of the US way of doing project management & bidding (FAR). 

Estimation and Project Control Expert, WYG Turkey, Managing All Local and International prestigious Projects

G
Gün Göksu 👤 Member for 21 years 2 months
START Date
END Date

WYG International (Consultancy)

Consultant. Bidding Team member responsible for the scheduling, resourcing & cash flow analysis of all technical projects bids. Coordinator of all active IPA awarded projects awarded (three projects total contract value ~9million Euro). Project Coordinator also working as Senior Expert for Cost control & Scheduling. Trainer and go to guy for Primavera, MSProject, MSExcel and other project control tools. All three projects consisted of waste water treatment plants and collecting network 

Planner, ENERJISA, Kusakli Dam Project

A
Akif UFUK 👤 Member for 9 years 7 months
START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
750
Experience Hours (Forensic Analysis)
750

I am working at the Technical office department for the Construction of Dam Project.

I am preparing master work schedule and update it. Also some other schedules for the method statement, to be prepared for each structure. Furthermore, i am supporting claim department by preparing time delay analysis.

project controls , 3 different companies, hq

M
Muguet Y 👤 Member for 14 years 7 months
START Date
END Date
Experience Hours (Planning & Scheduling)
1400
Experience Hours (Cost Management)
14000
Experience Hours (Forensic Analysis)
300

NOTICE:

The content of this Module from the Guild of Project Controls Compendium & Reference (GPCCAR) is currently available to:

Muguet Y

M
Muguet Y 👤 Member for 14 years 7 months
First Name
Muguet
Last Name
Y
Professional Since
Oldest experience
Years Experience
3

Been working project controls for the past 9 years.

Project management specialist, Pp Pmc, HQ

M
Muguet Y 👤 Member for 14 years 7 months
START Date
END Date
Experience Hours (Planning & Scheduling)
750
Experience Hours (Cost Management)
850
Experience Hours (Forensic Analysis)
0

Project Management Specialist at the HQ. Prepared budgets and schedules for company's ongoing and upcoming projects.                                           

Project management specialist, Pp Pmc, HQ

M
Muguet Y 👤 Member for 14 years 7 months
START Date
END Date
Experience Hours (Planning & Scheduling)
750
Experience Hours (Cost Management)
850
Experience Hours (Forensic Analysis)
0

Project Management Specialist at the HQ. Prepared budgets and schedules for company's ongoing and upcoming projects.