Philippines (AS.PH)

PH

Application Engineer / Planner / Primavera Application / Trainer, Saudi Oger Limited/ SCC/ J&P , 1. 30 Floor High Rise Building Construction

START Date
Experience Hours (Planning & Scheduling)
20200
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

 Create a Plan schedule of the Project using Primavera P6.

Update the Project by its Time Schedule in Physical Progress.

Monitor the Project Construction on the current status by analysis and evaluation of each activity.

Application Engineer / Planner / Primavera Application / Trainer, Saudi Oger Limited/ SCC/ J&P , 1. 30 Floor High Rise Building Construction

START Date
Experience Hours (Planning & Scheduling)
20200
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

 Create a Plan schedule of the Project using Primavera P6.

Update the Project by its Time Schedule in Physical Progress.

Monitor the Project Construction on the current status by analysis and evaluation of each activity.

Packaging Foreman, Philippine Polypropylene Inc., Logistics Operation

START Date
END Date

Packaging Foreman -Philippine Polypropylene Inc.

 (Nov.17, 2010- May 16, 2011) Pafc-Pnoc Batangas Dos Mariveles Bataan

  • Responsible for the overall operations of the packaging section with the end in view of maximizing productivity and ensuring good packaging quality.
  • Ensure packaging equipments are in good condition, available spare and raw materials.
  • Preventive Maintenance on the packaging equipments.

Planning Engineer/ SAP Specialist, Linde Philippines, SAP PM Process and Implementation, SAP PM Data gathering, upload a Testing

START Date
END Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
900
Experience Hours (Forensic Analysis)
600

Maintenance Planning Engineer / SAP PM Specialist

Linde Philippines (Linde Group) Reliability- Engineering Department

January 16, 2013- January 1, 2015- KM.47 Sampaloc, Apalit Pampanga Philippines