UEM Builders Berhad Planner
Current Role
MY
In-charge for the project’s preparation of Master and Work Programs incorporating all the resources including budget particulars, progress evaluation and forecast, provide and deliberate monthly management level reports, delegate tasks and assist the Project Control Team in scheduling and technical matters, submit proposal and summarized plan of action to achieve targets
Project Involved (Incorporating Structural, Architectural, Piping, Mechanical [Equipment], Electrical and Instrumentation Works):
Works sequencing and developing Level-3 & 4 Construction Schedules, manpower and equipment calculation and loading, progress monitoring and measurement on weekly and monthly basis; presentation and deliberation of weekly and monthly reports, likewise, highlight area of concerns and submit mitigation plans to meet target progress
Project Involved (Incorporating Structural, Architectural, Piping, Mechanical [Equipment], Electrical and Instrumentation Works):
EPCC of Putrajaya Precint 1 Cogeneration/District Cooling System Annex Plant (Stage 1 & 2)
Developing Level-4 Working Schedule using the agreed Level-2 Master Schedule (maintaining the commencement and completion milestone dates of key activities); set-up new weightage, manpower and equipment calculation and loading; progress monitoring, updates and reporting by weekly and monthly basis; likewise, highlight major issues and concerns, and propose solutions against drawbacks to improve progress
Projects Involved (Incorporating Structural, Architectural, Piping, Mechanical [Equipment], Electrical and Instrumentation Works):
Handling all planning & schedule aspect for all the infrastructure projects of the Company, which included (Pre‐tender – Level 1 & 2 Planning) presentation, methodology, preliminary schedule & resource allocation plan, (Post Contract) master work program, details work program support to project monitoring and progress status report, & etc…
Projects Involved: ‐
Handling all planning & schedule aspect for assigned project, Scheduling – tender outline program, preliminary and construction work program, Project tracking – project monitoring and progress status report, Financial – cash-flow plan, forecast & tracking, Contractual – contractual disputes & EOT claims, Execution – Mitigation & acceleration plan, & etc…
Projects involved:‐
• (Infrastructure Works – Government Project) Jalan Pos Betau – Lembah Bertam, Pakej 3: Kg Susu – Sg. Bertam (JKR Project) (RM 246 million)
(Works Package Contract – Underground Railway Track & Station Construction) (KVMRT – MRT system at Klang Valley) Projek Mass Rapid Transit Lembah Kelang : Jaran Sngai Buloh – Kajang, Works Package Contract – Underground Works (Tunnels, Stations & Associated Structures) Between Semantan North Portal and Mulari South Portal – 9.5 km (8.2 billion)