Project Manager / Contractors Engineering Manager, Faber Maunsell AECOM, Waterloo International Terminal Conversion Link between Platforms 19 & 20 - GRIP Stage 4 Outline Design
START Date
END Date
At Waterloo, Network Rail (NR) planned to incorporate redundant International Terminal platforms into the adjacent domestic station. The first phase converted a single platform (20) to accommodate domestic train services and provided access to it.

NR’s objective was to operate services from this platform by December 2008, keeping within the development budget set for them by the Department for Transport (DfT).