Taweelah - Fujairah Gas Pipeline Project

Project controls manager, Stroytransgas, Taweelah - Fujairah Gas Pipeline Project

START Date
END Date

Performing planning and project control activities for Taweelah – Fujairah Gas Pipeline Project, overall management of Project Control department.

Responsible for the following scope: 245 km of 48"-gas and 1.2 km of 40”-gas onshore pipelines construction, including 9 combined block valve sites.

Assuming responsibility for planning and scheduling project preparation and execution as well as procurement, supply, construction and commissioning activities including relevant documentation.

Defining relevant interfaces.