Standardization and Certification - SEC Special Project - Storage Plant and Supply Network of Biogas - CCU Chile - Planta Temuco

SENIOR PROJECT MANAGER PMP® PMO, Ingeniería Larrañaga E.I.R.L., Standardization and Certification - SEC Special Project - Storage Plant and Supply Network of Biogas - CCU Chile - Planta Temuco

START Date
END Date
Experience Hours (Planning & Scheduling)
250
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
150

Project Name: Standardization and Certification - SEC Special Project - Storage Plant and Supply Network of Biogas - CCU Chile - Planta Temuco.

Project Goals: Biogas plant certification, according to Chilean law.

Project Results: iogas plant regularization and registration according to SEC.