Decomissioning project of INPP

Strategic planning group leader, Ignalina Nuclear Power Plant, Decomissioning project of INPP

START Date
END Date
Experience Hours (Planning & Scheduling)
2150
Experience Hours (Cost Management)
650

Strategic planning group leader

Integrated decommissioning Program (Mega-project) decommissioning scenarios (what-if scenarios) developing. Modelling and studying of different negative impacts or restrictions on total cost and critical path. Among those are inflation impact, technical uncertainties, funding lack and others.  Developing new proposals for decommissioning strategy yearly update process.