Senior Planner

Senior Planner

Senior Planner , London Underground Limited, Power, Communication and Cooling Upgrades

START Date
END Date

Current Role: Senior Planner for LU Power Upgrades

Former roles:

Senior Planner for Cooling the Tube Upgrades (LU)

Scheduler/Analyst for LU Programmes Assurance Office

LU - PP BCV/SSL Claims Manager

LU - Company Procurement: Procurement Agent

TfL Momentum: Programme Manager

LU - PFI Central Team: Support Manager

LU - Connect PFI: Commercial Team/Risk Support Manager

Senior Planner, Balfour Beatty Major Projects, (LUL/Metronet Affiliates Project) London - Station Refurbishments

START Date
END Date
Experience Hours (Planning & Scheduling)
1900
Experience Hours (Cost Management)
350
Experience Hours (Forensic Analysis)
650

Secondment to Metronet - the management contractor working in an alliance to carry out works to 140 stations on the London Underground Limited (LUL) Network. Value £1.4 billion.

Senior Planner, Atkins Rail, North London Line

E
Emma Seaton 👤 Member for 20 years 9 months
START Date
END Date

Currently employed as Project Planner in the York Rail office of Atkins Ltd., working on bid and project programmes, including Peterborough Lineside Renewals; Signalling enhancements on West Coast Main Line routes and Birmingham International; Telecomms FTN cable and route surveys; and Multi-discipline work on Kettering South track reinstatement, Birmingham New Street, Edinburgh Waverley, and Nuneaton Chord.

Senior Planner, Balfour Beatty Civil Engineering, East London Line

START Date
END Date
Experience Hours (Planning & Scheduling)
1400

East London Line Extension. Value £360 million for Transport for London. Upgrade and extension of the existing East London Line Railway. Responsible for the construction planning for 2 of the 3 sections. Work included civil structures, depot construction, permanent way, signalling, telecoms & power.

Senior Planner, Eskom CED, Open-Cycle Gas Turbines (5 off) Power Station Build

START Date
END Date
Experience Hours (Planning & Scheduling)
1000

• For J&M Project Management Services, performing a site-based planning function for the successful completion of the ‘ESKOM Gas1’ Project (5 new Open-Cycle 150MW Gas Turbine Generators) at Ankerlig Power Station in the Western Cape of South Africa.
• Creating detailed schedules for various aspects of the above project i.e.

Senior Planner, Foster Wheeler, DSM Zealand Project IN CHINA

F
fhy frank 👤 Member for 17 years 7 months
START Date
END Date
  • Participate in 7 projects, 5 foreign projects and 3 involved from detail design to mechanical completion.
  • The planning and scheduling methodology is a high level of proficiency for EPC project.
  • Advances planning experience for various project was referred to industrial pharmaceutics, petrochemical and chemical building etc.
  • Skill in schedule software tools by using P3~6 and Microsoft Project/Excel etc.

Senior Planner, CrossRail Project, Crossrail Project

START Date
END Date

Responsible for development of detailed plans, networks and programmes for surface and sub-surface construction, NATM and bored tunnelling activities, and mechanical and electrical systems installations and commissioning works.



Responsible for ongoing development of project control and cyclic progress reporting & change control systems. The network manager for the programming / structure coding of infrastructure and system installation and commissioning works.