Project Planning and Controls, Halcrow Construction, Crossrail
START Date
END Date
- Development and maintenance of Project Control Schedule (PCS) in the Project Control (P6) database in accordance with appropriate procedures, guidelines and instructions. Updated and progressed programmes at a minimum of 4 weekly intervals in line with Crossrail’s timetable of reporting
- Ensured that project schedules accurately reflect the scope of the project in accordance with an agreed WBS and are of sufficient detail to enable project progress to be accurately monitored, reported and communicated
- Agreed lower level schedules with task ma