Area Planning Engineer

Area Planning Engineer, ORIENT Energy System (Pvt.) Limited (OES), Construction of THATTA POWER PLANT, DADU POWER PLANT, OMNI POWER PLANT

START Date
END Date
Experience Hours (Planning & Scheduling)
4900
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50
  1. Develop, review and maintain the project plans and baseline schedules using Primavera
  2. Monitor progress throughout the construction process on a weekly basis and compare with work plan (Actual vs Baseline Schedule)
  3. Identify and review regularly, critical and sub-critical activities and monitor its impact on overall plan
  4. Develop and maintain project change control and review scope change requests for impact on schedules and the critical path of the project.
  5. Submitting planning package with all allied documents
  6. Ensuring availability of drawings in l

Area Planning Engineer, PetroSA (PTY) Ltd, Refinery Shutdown

START Date
END Date
Experience Hours (Planning & Scheduling)
10400
Experience Hours (Cost Management)
1400
  • Shutdown And Turnaround Planning And Execution (Implementing 7 Phases Planning Cycle).

 

  • Compilation of Shutdown and Turnaround Schedules (Bar Charts Using Primavera And Or Ms Projects.

 

  • Originate And Review Planning And Scheduling Documentation.

 

  • Facilitation the Execution of Shutdown and Turnaround Plans and Schedules.
  • Reporting and Continuous Improvement of Maintenance Kpi’s.

 

  • Provide Guidance To Formulation Of Long Term Outage Plan.

 

Area Planning Engineer, VCS Quality Services Pvt. Ltd., DNEPL Project

A
Abhay Singh 👤 Member for 7 years 9 months
START Date
END Date
Experience Hours (Planning & Scheduling)
10800
Experience Hours (Cost Management)
900
Experience Hours (Forensic Analysis)
50
  • PMC services of Overall Cross-Country Pipe Line to Reliance Gas Pipelines Ltd. (India), for EPC Dhaej Nagothane Ethane Pipeline (DNEPL) consist of pipeline of 12 inch and combined length of 480 Kms.

Area Planning Engineer, KALPATARU POWER TRANSMISSION lIMITED, PRP-AMD

A
Abhay Singh 👤 Member for 7 years 9 months
START Date
END Date
Experience Hours (Planning & Scheduling)
3400
Experience Hours (Cost Management)
400
Experience Hours (Forensic Analysis)
0
  • Engineering, Procurement & Construction Services of Cross Country Pipe Line to Oil & Natural Gas Corporation Ltd. (ONGC) India, for Pipeline Replacement Project of Ahmedabad Assets (PRP-AMD), consist of pipeline of 4, 6, 8, 12, & 14 inch and combined length of 248 Kms.

Area Planning Engineer, Sicim Kazakhstan, FGP /WPMP

START Date

Ø  Main scope includes Engineering, Procurement and Construction work (Temporary facilities, Civil, UG Piping, Electrical, Instrument and Pre-Commissioning).

Ø  Able to understand the Technical Scope of work, Scheduling / Planning the appropriate set of activities and ensuring on timely completion of Project by Operating  Primavera Software.

Ø  Developing of EPC Master Schedule using Primavera P6 Software and updates on weekly basis.

Area Planning Engineer, Network Rail Ltd, Southern Power Supply Upgrade Project

START Date
END Date
Experience Hours (Planning & Scheduling)
1750
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
0

A member of Network Rail Southern Region Power Upgrade Project, resposible for the development of programmes to support HMRI Railway Safety Regulations were met regarding the replacement of Mark 1 Slam Door Trains.

Area Planning Engineer, TCO, FGP/WPMP

I
Ian Lawton 👤 Member for 20 years 4 months
START Date
Experience Hours (Planning & Scheduling)
1550

Working on the Engineering side of the Future Growth Project (FGP) in the areas of Brownfield, Overhead Power Distribution (OHPD), Fibre Optic Backbone (FOB) and Tie-ins. My role for the client (TCO) involves closely monitoring the KPJV planning element along with other specialist contractors involved with the Engineering aspect of the project. I am also a focal point between Engineering and Construction (for my areas)....