Construction Project Planner / Senior Planner, Geoffrey Osborne Limited, Ross Planning contract for Geoffrey Osborne (directly as follow on from A565 contract) – A57-A628 Trans Pennine surveys, A1 Northumberland surveys, and others, for Highways England u
Starting from MS Project export from P6 (by others), resolve anomalies, make a Clause 31 programme, then update to Clause 32 programmes as required.
Construction Project Planner / Senior Planner, Geoffrey Osborne Limited, Ross Planning contract for Geoffrey Osborne (directly as recommended by an employee) – A565 North Liverpool Key Corridor roads upgrade in Liverpool & Sefton, programme in MS Project
Normal
0
false
false
false
EN-US
X-NONE
X-NONE
Construction Project Planner / Senior Planner, Volker Laser, Ross Planning contract for VolkerLaser (directly as worked with them previously, see below) – M1 River Trent Viaduct Column Strengthening, programme reorganisation in MS Project
The existing programme had some spurious link as the order of works had been dragged from an existing resourced programme, I sorted out the order and linking, and submitted this to VL for consideration, after 3 iterations this was submitted to their Client. The initial plan was for me to update this over several months, however this request was never made by VL
Construction Project Planner / Senior Planner, Carillion Kier JV, Ross Planning contract for Carillion Kier JV via Project Resource – Smart Motorway M6 Junctions 16 to 19, verge programme in P6 and ChainLink
Normal
0
false
false
false
EN-US
X-NONE
X-NONE
Construction Project Planner / Senior Planner, Tarmac Construction, Ross Planning contract for Tarmac via Hays Recruitment – Surfacing for M5 Junction 4a to 6 smart motorway in MS Project
Normal
0
false
false
false
EN-US
X-NONE
X-NONE
Construction Project Planner / Senior Planner, SPI Appleton via Minstrell Recruitmant, Ross Planning contract for SPI Appleton via Minstrell Recruitment – Mersey Gateway As-builts and other analysis in MS Project
Normal
0
false
false
false
EN-US
X-NONE
X-NONE
Construction Project Planner / Senior Planner, Eurovia Contracting, Ross Planning contract for Eurovia Contracting North via Project Resource – various new contracts & updates out of Peterborough and Telford offices, programme development & analysis in MS
Eurovia’s current planner is leaving, thus some existing projects need updating, and others will need tender, Clause 31 or 32 programmes, all done in MS Project 2013. This will include CE programmes to substantiate delays. No work requested since August 2015
Paul Ross
Summary
Planner (Senior/Lead Planning Engineer) of wide civil & rail engineering experience, from roads to structures, marine breakwaters and dock structures, some experience in tunneling, process engineering. Also have temporarry works experience to BS 5975 and BS 5873, not used much since 1994
Specialties
Primavera P3 & P6, SureTrak, Microsoft Project, ChainLink, some Asta Powerproject
Construction Project Planner / Senior Planner, Morgan Sindall, Ross Planning contract for the Morgan Sindall portion of bmJV via Project Resource – Update programmes for the A14 Kettering Bypass, using P6