Roads / Tunnel / Bridge

Planning Engineer, Leighton Contractors (Asia) Limited, Seg.8.1 North Luzon Expressway Project

J
Joseph Ador 👤 Member for 15 years 10 months
START Date
END Date

Construction of North Luzon Expressway Connecting Mindanao Avenue and Existing NLEX. Contract including construction of 2 bridges, toll plaza, clover lift (8 ramps), Drainage and Slope Protection Structures and Employers Representative Building Structures. It's a great challenge in the part of the contractor to build an expressway in the Highly Urbanized City of Manila, however, due to good management and operations experience the project was delivered on time.



 Engage in projects tender, coordinate with engineering manager in establishing working construction methodology.

Planning Engineer (Main Office - Tripoli - Libya), Joannou & Paraskevaides (Overseas) Ltd – Cyprus (J&P), Supply and Replacement of Drinking Water Pipeline at AZAWYA Refinery Company

START Date
END Date

Project:(JP 148) Supply and Replacement of Drinking Water Pipeline including Supply and Laying of Irrigation water pipeline in Refinery and Township Area at AZAWIYA.

Ram Krishna Sitaula

First Name
Ram Krishna
Last Name
Sitaula
Oldest experience
Years Experience
42
  • Graduated as an architect in 1993;
  • 5 years work experience as an architect;
  • completed master degree in Infrastructure Planning (1999- 2001);
  • 3 years of Project Manager expereince in Urban & Environmental Improvement Project, Nepal (2003 - 2006)
  • UNV expereince- UNMIL, Liberia (2006)
  • UK Expereince (2007- to date)
  • 10 years of expereince in project management as a planner (consultant, contractor, cleint)
  • Recently professionally qualified Eng TECH, TMICE specifically demonstrating planning role.
  • Project co

Senior Planner, BAM Nuttall Ltd., London 2012 Olympics Project - Structures Bridges & Highways

START Date

Current Role: Senior Planner at BAM Nuttall Ltd - Structures, Bridges & Highways, London 2012 Olympcis Project, Stratford; October 2008 - to date.

Duties & Responsibilities: Prepare tender programme, contract programme with chnage management, EVM, NEC 3 Contract, Delay analysis, prepare and update Compensation event and quantity tracker, Project controls. 

Recently professionally qualified (Nov 2011) Eng TECH, TMICE showing competence in NEC 3 contract programme management as a planner role.

FIELD ENGINEER / BILLING ENGINEER, Jaiprakash Associates Limited, 1020 MW Tala Hydroelectric Power Project Bhutan

START Date
END Date

 

·      Project: 1020 MW Tala Hydroelectric Project                                (May 2004 to May 2007)

Engineer, AerodromDorStroy ZAO, Airports across Russian Federation

START Date
END Date

• Take Offs;

• Preparation of tenders, Tender invitation, Quote evaluation;

• Programming and Tracking project timelines;

• Preparation of daily, weekly and monthly reports;

• Obtaining and comparing quotes from trades, sub-contractors and suppliers, generating purchase orders;

• Forecasting labour loads, material and labour costs calculations and analysis, estimate plans development;

• Ensure sub-contractors/suppliers conform to project specification/standard requirements.

 

CIVIL / PLANNING ENGINEER, MT Hojgaard, Cable stayed bridge

START Date

Work Experience

1/ Rao II cable stayed bridge project (ODA project) - MT Hojgaad's Office management-Denmark Contractor- Apr 2010 - Present

Position: Planning Engineer.



- Preparation and control Master schedule, Production schedule, Weekly schedule in Cable stayed bridge project.