Railway

Planning engineer for Bombardier Transportation, S.L., Silver Atena, London Underground's Resignalling Project

START Date
END Date
Experience Hours (Planning & Scheduling)
850

Planning engineer for the CBI (Computer Based Interlocking) subproject within the London Underground's Resignalling Project, awarded to Bombardier Transportation (Silver Atena's client). Total Project Budget: 350 millions of pounds. Functional duties to the Project Core Team -To support the Project Manager in discussions related to delays and/or improvements of the schedule. -To support the Project Manager or Supply Manager representatives communicating detailed schedule objectives or issues to suppliers.

Scheduler , AECOM Canada, Ltd., Simandou Iron Ore Project-Rail Road.

START Date
END Date
Experience Hours (Planning & Scheduling)
300

The AECOM Simandou Project is comprised of two principle components:
A 650 km-long Trans-Guinean railway to transport iron ore from the mine to the coast.
Rio Tinto (RTIO) contracted the engineering services to Fluor as an EPCM contract with AECOM as a sub-consultant.

Vanisadar Ibrahim

First Name
Vanisadar
Last Name
Ibrahim
Professional Since
Oldest experience
Years Experience
10
Telephone Number
+966560708760
LinkedIn Profile
https://www.linkedin.com/in/vanisadar-ibrahim-557929100?trk=hp-identity-name

·         Thorough and proficient in 16 Division Master Format of Construction Specifications Institute (CSI)

·         Contractor Method of Measurement (MOM) responsiveness

·         Detailed Take offs from working drawing     

·         Set up for Bill of Quantities or Materials (BOQ/BOM)

·         Set up Cost Price Breakdown

Project Quantity Surveyor , Contracting & Construction Enterprises Ltd., SAUDI RAILWAYS ORGANIZATION (SRO)Riyadh City, KSA: RUNNING REPAIR SHED, HEAVY REPAIR WORKSHOP

START Date
END Date
Experience Hours (Cost Management)
14000

·         Prepared detailed takeoffs from division 2 to division 13.

·         Advised and coordinate the procurement Engineer on procurement strategy.

·         Prepared a cost price breakdown for a new works not included in the BOQ.

·         Revised cost price breakdown for potential savings.

Senior Project Quantity Surveyor, Contracting & Construction Enterprises Ltd. (CCE), KSA:LOCOMOTIVE MAINTENANCE FACILITY EXPANSION, SAUDI RAILWAYS ORGANIZATION (SRO)Dammam City

START Date
Experience Hours (Planning & Scheduling)
600
Experience Hours (Cost Management)
20000

·         Analyzed bid drawing with approval or IFC drawing for cost comparison and for potential savings.

·         Prepared detailed takeoffs from division 2 to division 13.

·         Prepared the materials schedule for approval and request for quotation (RFQ).

·         Prepared a cost price breakdown for a new works not included in the BOQ.

Ian Cameron

I
Ian Cameron 👤 Member for 20 years 4 months
First Name
Ian
Last Name
Cameron
Professional Since
Oldest experience
Years Experience
13
Telephone Number
07786417844
LinkedIn Profile
in/ian-cameron-1b2a9532?trk=nav_responsive_tab_profile

Ian has 15years experience in project planning / project controls and 25years in the rail sector. He has the ability to communicate at all levels and has the skill set to both mentor & manage planning teams that deliver. He has a solid understanding of CPI & SPI, earned value techniques and analysis. Latterly analysing existing reporting, re-structuring and successfully implementing a suite of reporting tools.

Project Planner, Metronet Atkins Station Design Team, (LUL/Metronet Affiliates Project) London

I
Ian Cameron 👤 Member for 20 years 4 months
START Date
END Date

Metronet (ASDT)                                                                                                &nb

Senior Project Planner, Amec Spie Rail (UK), NwR Signalling Works Geographical Partnering Arrangement framework

I
Ian Cameron 👤 Member for 20 years 4 months
START Date
END Date

Amec Spie Rail (UK) Ltd                                                                                          Senior Planner