TAR Manager, CITGO Refining, Major Refinery Turnarounds
April 2011 – July 2012 – Coker 1 TA Manager- 59MM
- Overall Project lead responsible for Safety, Environmental, Reliability, Schedule and Budget.
- Set safety goals and communicated safety milestones daily.
- Project was completed with zero recordable Injuries, zero environmental incidents, zero issues during start-up
- Interfaced with contractors daily on performance, priorities and daily execution schedules.
April 2011 – November 2011 Sulfur B-Train TA Manager– 2.0MM