Doosan Babcock Planner
Current Role
Current Role
Schedule, cost, claims/backcharges, progress
Overseeing all planning and cost control issues relating to projects with values between $19 million and $1,295 million for Khursaniyah Gas Plant, the Hawiyah NGL Recovery project, the Berri Gas Plant Cogeneration project, the Haradh Gas Plant project, the Hawiyah Gas Plant Project and the Yanpet II Ethylene Expansion project; having the following responsibilities:
• Evaluating project documentation in the early stages, developing a chart of accounts and preparing a project budget for approval in accordance with company policy
SHARQ 3rd Expansion Project
Off site expansion control and planning, ARAMCO standards reflection and time delay and qualified work groups and personnel. (Under MMG)
Saudi-Kayan Petrochemical complex erection
Area 21 (Off Plot) : Pipe line Planning including Port Area Tank Farm Civil work Planning.
Area 22 (Modularization): Structural Work Modularization and Pipe Rack Erection.
Current Role