GulfSpic Project Controls Engineer

R
Ram Kumar 👤 Member for 18 years 10 months

5.8 years of experience in Project Management, Construction of Petrochemical, Refinery involving design, Engineering, planning, execution, coordination, inspection, commissioning activities etc... Also involving planning & preparation of Master, Micro and detailed Schedule for Construction, shutdown, Material & Spares procurement etc

CCC (Consolidated Contractors Company) Planning Manager

-     Preparation of Over All Detail Project Schedule in Primavera (With Resources Assignment & Budget Cost)

-     Preparing for detail construction works during shutdown for life plants development.

-     Updating of Schedule & Preparation of Catch-Up Plan and assisting Project Managers by indicating the trend of the Project Critical Path.

-     Preparation of the construction S-Curve.

-     Inter-Department Co-Ordination with Engineering, Procurement, Quality and Construction for smooth Progress of the Project.

Davy Mckee Corporation Planner

ARCO, Cost Engineer

          On Assignment to ARCO at Stornoway Isle of Lewis

(Offshore Fabrication Yard) Involvement in setting up Project Control System including checking and agreeing definitive estimates for CTR activities , unit rate negotiations and cost control procedures. Re-measurement of structural steelwork (jackets) Star rate agreement , interim & final valuations. Agreeing Progress against job cards , set up reporting system on Personal Computer

Davy Mckee Corporation Planner

East Berlin Flue Gas, Desulphurisation Project, Cost/Planning Engineer

Set up Project Control Systems using Artemis Pc, Lotus, Dbase III Software. Responsible for Maintaining Network logic, Progress Measurement, Additional works, Monthly Valuations.Preparation of networks for both Construction & Commissioning activities. "What if exercises", Close out Reports.

Davy Mckee Corporation Planner

Esso, Esso Fawley Residfiner Project, Planning Engineer

Petrochemical Process Plant

Part of Task Force to Re-assess work to completion. Instigate new Planning Network Artemis 6000 Set up Project control databases & Report specs. Preparation of Project/Construction Monthly Reports. Tracking progress against Plan using databases set up in Artemis, Dbase, Lotus Software.

Davy Mckee Corporation Planner

Shell, Shell Haven Naphtha Minus Project, Planning Engineer

Fast Track Petro Chemical Process Plant. Involving extensive use of PAU’s (Pre-assembled units).Instigate Level 3 Network for Work to go. Using OPENPLAN SOFTWARE. Including modifying standard reports to provide customised level 1,level 2 summary Bar charts, Resource Histograms etc. Special responsibility for Electrical & Instrumentation Subcontractor. Including Monitoring Weekly Progress, initially setting up of Job card system, attending weekly Progress

Parsons Planner

Ralph M Parsons, AMOCO gas Project C.A.T.S. , Senior Planner

On assignment London Office

Develop Engineering/Construction Networks/plan

Level 3/2 and set up Project Controls for AMOCO gas Project C.A.T.S. Teesside, using Primarvera Software P3 for Windows working in an alliance framework with Contractors to jointly develop integrated plan for all disciplines.



Aug-1993 May-1995 Statoil, Kalundborg Condensate Project, Senior Planner

statoil Planner

MW Kellogg Integrated Team, Asgard Project

Asgard Project Onshore Terminal Karsto Norway

On Assignment MW Kellogg Offices London

Develop Level 4 Overall Planning Network EPCS Contract

Engineering Fabrication Construction & Commissioning Activities

Using Primavera P3 Windows NT Making Full Use of Office 97 Software

Linking Access 97 via Btrieve Tables to Primavera Level 1 2 & 3 Roll Up Schedules

Transfer of Data to Company PIMS Information System (Access 97 Based)

Monte Carlo Risk Analysis Primavera Add In.