Oil / Gas / Power

Business Development Manager, Tyco International Thailand Ltd, Indochina Business Development-Fire & SEcurity, Marine

START Date
END Date
Experience Hours (Cost Management)
2900

Business Development Manager, Tyco International Thailand Ltd.

  • Developed selling prices for product for distribution, marketing brochures, compiled electronic catalogues CD ROM for client s and selected partners.

PROJECT ADMINISTRATOR, ODG PNG Limited, ANGAU Hospital Redelopment Project

START Date
Experience Hours (Planning & Scheduling)
2200
Experience Hours (Cost Management)
700
Experience Hours (Forensic Analysis)
100
  • Project setup initialization kicks start, project and document controls, and procedures, project calendars for meetings, deliveries and major milestones.
  • Preparation of level 2 schedules and schedule basis memorandum, 30 day look ahead schedules.
  • Coordinate with site team to capture daily and weekly targets and discuss deliverables with problem areas/issues to deliver as per budgets hours required.
  • Preparation of O&M and Training Manuals
  • Documetn controls for ODG and Aconex
  • Productivity reports<

Benito Agus Putranto

First Name
Benito Agus
Last Name
Putranto
Professional Since
Oldest experience
Years Experience
2
LinkedIn Profile
Benito A Putranto
Facebook Profile
Benito A Putranto

I am a civil engineer in oil and gas company. my skills are:

  • SAP2000
  • AutoCad
  • Project Engineering
  • Certified Gas Station Inspector

Assistant Engineer, PT. Pertamina (Persero), Bridge and Jetty Construction

START Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
300

My roles and duties:

 

1. Making an engineering design for project

2. Create Owener estimate for project

3. Monitoring and controlling project

/ Construction Project Planner / Senior Planner / Forensic Analyst, PT. Pertamina (Persero), Asset Integrity Projects

START Date
Experience Hours (Planning & Scheduling)
900
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
1000

Now my task is Asset Integrity System that set up to standarize integrity system on Pertamina Upstream subsidaries company that consist of various capacity production, background and located on scatter area of Indonesia.

Asset Integrity System that will built have key performance that must achieve and monitored regularly and will visualized on Integrity Dashboard which will be monitored by Upstream Director. Integrity performance of subsidary company can compare each other so we know which the best and the worst performance.

Arief Rachman

First Name
Arief
Last Name
Rachman
Professional Since
Oldest experience
Years Experience
4
Telephone Number
+62 811167185

I'm an electrical engineer and work at Pertamina since 3rd March 1992. Pertamina is oil, gas and geothermal company and now change to be energy company.

My experiences are related with engineering, operation and maintenance of electrical power plant, electrical transmission and distribution network, electrical load calculation and lightning protection system. Besides that, I have experiences in pipeline cathodic protection, produced water injection system, oil and gas transportation system, oil and gas sharing facilities system.

/ Construction Project Planner / Senior Planner / Forensic Analyst, Pertamina EP, Offshore Power Plant

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
2000

On Offshore Gas Turbine Generator Set Project, I joint on mid of construction work. The project scope is to decommissioning the existing generator set and to construct 4 set new Gas Turbine Generator System complete with panel control set. The obstacle is limited space and no stop oil and gas production operation.

To solve problem limited space, we choose the GTG with big capacity and small size. For no stop production operation, we use external power plant that we set up the generator set on the barge with subsea cable. That condition will make the problem if the weather is bad.