Forensic Claims

Forensic Planner / Delay Analyst, Abesque, Simcoa Furnace 3 Expansion Project

START Date
END Date
Experience Hours (Forensic Analysis)
250

Simcoa Furnace 3 Expansion Project Brownfields upgrade to Simcoa Furnace 3.

Forensic Planner, (Specific Assignment), 04/2012 to 06/2012

Defense Audit on EOT time claim received from Sub-Contractor regarding late free issue materials and late fabrication effects on construction

Forensic Planner / Delay Analyst, Fortescue Metals Group, T155 Jetty Project

START Date
END Date

T155 Jetty Project – 305 Tonne Jetty Improvement Project.

Forensic Planner, (Specific Assignment), 03/2012 to 05/2012

Defense review for owner against Jetty Construction contractor EOT claim

Forensic Planner, Brookfield Multiplex, Maundering Weir Water Treatment Plant Project

START Date
END Date
Experience Hours (Forensic Analysis)
750

Maundering Weir Water Treatment Plant – 165,000 Cubic Meters of water per day Water Treatment Plant.

Forensic Planner, (Specific Assignment), 02/2012 to 06/2012

Integrate Bill of Quantity data to progress schedules to assist client in development of Extension of Time claim case due to large change in scope and delay in design

Forensic Planner, CTEC, Merredin Power Station Project

START Date
END Date
Experience Hours (Forensic Analysis)
200

Merredin Power Station Project. 82MW PowerStation Project in Western Australia.

Forensic Planner, (Specific Assignment – Part time consulting role)07/2012 to 09/2012

Defense EOT claim preparation for client against contractor due to late delivery of equipment

Forensic Planner, Ertech, Marandoo Dewatering Project

START Date
END Date
Experience Hours (Forensic Analysis)
1250

Marandoo Dewatering Project – 24km pipeline with 27 bore pumps, Transfer & booster pump stations in Western Australia.

Forensic Planner, (Specific Assignment) 06/2013 to 03/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Forensic Planner, Ertech, Chevron Wheatstone Project

START Date
END Date
Experience Hours (Forensic Analysis)
150

wheatstone villageChevron Wheatstone Construction Village Buildings & utilities Project. Western Australia.

Forensic Planner, (Specific Assignment), 01/2014 to 03/2014

Preparation of Extension of time claim schedule in “Impacted as Planned” format.

Forensic Planner, PIHA, RIO-TINTO Cape Lambert Expansion Project

START Date
END Date
Experience Hours (Forensic Analysis)
600

RIO-TINTO Cape Lambert Services Contract Construction Project of Piping and Cable infrastructure at Point Sampson in Western Australia.

Forensic Planner, (Specific Assignment), 08/2013 to 06/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Forensic Planner / Delay Analyst, Lend Lease, Cape Lambert Rail Expansion Earthworks

START Date
END Date
Experience Hours (Planning & Scheduling)
100
Experience Hours (Cost Management)
350
Experience Hours (Forensic Analysis)
1000

Forensic Planner(3 months full time & as required through Mediation process), 6/2013 to 2/2014

Defense and implementation support for “Extension of Time” claim

Selected Accomplishments:

Introduction of Bill of quantities values of various types of earthworks values from estimates into various Primavera updated schedules.

Conversion of various earthworks units of measure into “Mass Haul” values and re-introduce these values into various updated schedules.

Principal Forensic Planner, Chevron, Gorgon LNG PROJECT: AU$54 Billion Gas Plant Construction on Barrow Island in Western Australia.

START Date
END Date
Experience Hours (Planning & Scheduling)
550
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
4300

Principal Forensic Planner,12/2014 to Present

Management of all planning activities and defense of high value claims from multiple contractors as part of a 4 member defense team.



Selected Accomplishments:

Set up and management of dedicated Primavera-based SQL databases for multiple projects spanning 5 years in defense of multimillion dollar claims.

Senior Planning Consultant, Sporle Consultancy Services (SCS), (various projects)

START Date
Experience Hours (Forensic Analysis)
13250
  • Windows Analysis - Extracting, analysing and comparing critical paths of contemporaneous schedules.
  • Review contract documents and identify requirements regarding project controls and Entitlement to EOT and associated costs.
  • Carrying out appropriate analytical techniques to demonstrate Contractor’s Entitlement to EOT and associated costs.
  • Prepare Statement of Claims (detailed reports and analyses).
  • Provided assistance to the appointed Expert in relation to delay assessment on a Contractor’s Claim.
  • Perform delay a