Civil / Building / E&M

Junior Engineer, Fathy Abd Rabu Construction Berau, (various projects)

H
Hassan Emam 👤 Member for 15 years 9 months
START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
1500

I have worked on multiple building construction projects in Egypt as a junior engineer. I participated in three medium sized projects all in Alexandria

Head of Planning, Besix, (various projects) @ all in the Middle East

H
Hassan Emam 👤 Member for 15 years 9 months
START Date
END Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
3000
Experience Hours (Forensic Analysis)
2000

Worked in Middle East region for BESIX in several exciting projects as Business Bay Crossing, The Adress hotel, Doha Convention Center, Arabian Business Infrastructure and some marine works

Tim Readman

T
Tim Readman 👤 Member for 23 years 1 month
First Name
Tim
Last Name
Readman
Professional Since
Oldest experience
Years Experience
45

I have been working as a construction planner for 40 years in Uk, Middle East and Australia. I have a degree in building from University of Aston and professional certificate of Arbitration from University of Adelaide.

I have worked mainly for construction companies John Laing, Tarmac, Trocon, Cementation, Jennings, Fletchers, Built Environs MACE, Baulderstone & Ahrens as an employee.

vikram verma

First Name
vikram
Last Name
verma
Professional Since
Oldest experience
Years Experience
46

Construction Projects Management Professional. Working freelancer Project Managers for construction management of building, industrial, commercial, retail, hotels and hospital projects...

Head- Projects management, Consultant / Contractor - Self Employed, Residential, commercial, industrial

START Date
Experience Hours (Planning & Scheduling)
40000
Experience Hours (Cost Management)
40000

Working freelance Project Manager with an Architectural firm based in India.

Looking for clients who wants to set up their spaces in India.

Project Manager, Blue City Company, Blue City Project

START Date
END Date

Project Manager, Blue City Project

Sawadi, Oman— Dec 2008-Sep 2010

Blue City is a $15 billion megacity project spread over 32 square kilometres and 16 kilometres of coastline along the coastal region at Al Sawaadi. The city will include 20 hotels, hospitals, and university. It will have shopping centres, marina, and schools, golf course, etc. The project manager is responsible for the development of Phase 1 of the project which includes 5-star hotel, residential apartments, golf course and villas.

Assem Osman

First Name
Assem
Last Name
Osman
Professional Since
Oldest experience
Years Experience
8
Guild Accreditation
GPC Member
LinkedIn Profile
https://www.linkedin.com/in/assem-sherif-pmi-sp-psp-b03bab29

Management Skills:

  • Time planning using C.P.M and L.O.B and PERT
  • Developing 4D schedules
  • Delay & Time Impact Analysis
  • Cost Estimation Project finance using Cash flow Analysis
  • Value engineering studies
  • Resource allocation , Leveling and Planning
  • Cost and Time control using Earned Value Analysis
  • Risk management ( Risk Identification-Risk Qualification-Risk Quantification using Monte Carlo simulation using Risky Project & Primavera Risk Analysis Software- Risk Response Plan)

Senior Planner, Bateman, SNC-Lavalin, Evra Consulting, Kusile Coal Fired Power Station – South Africa

START Date
Experience Hours (Planning & Scheduling)
6600

I currently perform the role of a Senior Planning Consultant for a specilist project Planning consultancy called Evra Consulting.

I occupy a role which involves business development and plannig supervison. 

EVRA COnsultancy offers planning services primariliy in the Construction, Power and Infrastructure. Inaddidtion to this the firm specializes in Forensic Planning services. 

Construction Planner, Group Five Coastal, (various projects)

START Date
END Date

· Recently started with Autodesk software & Linking the CCS programme to a 3D Revit Model         

Studying tender document (Contract, drawings, specifications, reports etc)

·         Extracting information which might be risk to our business unit, identifying opportunities and defining whether or not the timeframe given is achievable