Civil / Building / E&M

Bid/Project Planning Engineer, Almoayyed Air Conditioning Qatar, Vendome Mall

START Date
  • Study the contract documents and understand the nature of the job along with start date and end date.
  • Review the IFC drawings along with the PE for an understanding of the scope of works.
  • Prepare the project charter and study the BOQ for program preparation
  • Prepare the works program (WP) along with cost and labor loaded in discussion with PE,PM and Higher level management in 14 days from the date of receiving the main contractor program, and follow up main contractor for the approved program and should u

Akhil Chandran

First Name
Akhil
Last Name
Chandran
Professional Since
Oldest experience
Years Experience
4
Telephone Number
+974 33034755
Facebook Profile
Akhil Chandran
  1. The ability to work as part of a team
  2. Good leadership skills
  3. The ability to motivate others and make them aware of an overall aim
  4. Attention to detail
  5. Good communication and interpersonal skills
  6. The ability to see the broader picture and work out how individual elements should operate as part of an overall aim
  7. The ability to remain flexible and calm under pressure and in the face of a tight deadline
  8. Creativity
  9. Good numeracy skills
  10. Good literacy skills
  11. A technical mind
  12. The motivation and desire to sol

Bid/Project Planning Engineer, Almoyyed air Conditioning, Vendome Mall

START Date
  • Study the contract documents and understand the nature of the job along with start date and end date.
  • Review the IFC drawings along with the PE for an understanding of the scope of works.
  • Prepare the project charter and study the BOQ for program preparation
  • Prepare the works program (WP) along with cost and labor loaded in discussion with PE,PM and Higher level management in 14 days from the date of receiving the main contractor program, and follow up main contractor for the approved program and should u

Advisor - Planning and Scheduling, Maks automation, Design of Automatic pick and place robots

START Date
END Date
  • Prepare the Daily, Weekly and Monthly reports
  • Prepare the baseline program and update the work progress as per the contract
  • Monitor the site activities as per the baseline program
  • Monitor and tracking the delivery of materials
  • Ensured that all site operations were carried out in safe productive manner
  • Monitor critical activities based on the project schedule and advise project management.
  • Report to the Project Manager about the cu

emma kerr

E
emma kerr 👤 Member for 8 years 3 months
First Name
emma
Last Name
kerr
Professional Since
Years Experience
0

Construction and Fit out planner.

18 years industry experience.

Asta power project user

Planning Manager or Senior Planning Manager, Joannou & Paraskevaides (Overseas) Ltd, 1. Building Construction

START Date
Experience Hours (Planning & Scheduling)
36000
Experience Hours (Cost Management)
36000
Experience Hours (Forensic Analysis)
36000

Senior Planning Managern - Incharge of planning, analysis, reporting, monitorig, mitigation & EOT for the project in 20 site with a total of more than 1000 nos of buildings.

Alexander Campos

First Name
Alexander
Last Name
Campos
Professional Since
Oldest experience
Years Experience
11
Guild Accreditation
GPC Member
Telephone Number
511944897527
LinkedIn Profile
www.linkedin.com/in/alexandercc
Twitter Profile
https://twitter.com/shandercc

Communication: Verbal and written, working with staff, reporting progress or problems to the client, or negotiating with stakeholders of the project,

Leadership:  Ability to lead, motivate and resolve personal conflicts,

Assistant Cost Control & Change Management, AYG EDIFICACIONES SAC, RESIDENCIAL LOMA VERDE

START Date
END Date
Experience Hours (Planning & Scheduling)
800
Experience Hours (Cost Management)
800
Experience Hours (Forensic Analysis)
150

RESIDENCIAL LOMA VERDE (Assistant Cost Control & Change Management)