Civil / Building / E&M

Juan Antonio López de Vergara

First Name
Juan Antonio
Last Name
López de Vergara
Professional Since
Oldest experience
Years Experience
50
LinkedIn Profile
https://www.linkedin.com/in/juanlvf/?locale=en_US

Master in Civil Engineering, Project Controls Engineer. I currently channel my efforts towards the execution, planning and economical management of projects in the construction industry. I seek positions in the area of civil engineering related with Project Management, with a special focus in an Project Controls position managing the cost and program with the aim to reduce risk and increase productivity.

Lead Planning Engineer, Ferrovial Agroman Australia, Harwood Bridge

START Date
Experience Hours (Planning & Scheduling)
5900
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
400
  • Ferrovial Tender Office, Tender for Western Sydney Airport & Nowra Bridge Update. (Dec 18 – Actual)
  •  B2B Project Controls Initiative.

Ahmed Saudagar

First Name
Ahmed
Last Name
Saudagar
Professional Since
Oldest experience
Years Experience
50
Guild Accreditation
GPC Member
LinkedIn Profile
https://www.linkedin.com/in/aksaudagar/
Twitter Profile
https://twitter.com/aksaudagar

PROFILE

A Project Management Professional and a Chartered Engineer with ample exposure and professional experience spanning highly prestigious and fast track construction projects in the Middle‐East and Europe.

Kevin Sung

K
Kevin Sung 👤 Member for 6 years 3 months
First Name
Kevin
Last Name
Sung
Professional Since
Years Experience
0
LinkedIn Profile
https://www.linkedin.com/in/kevin-sung-9700461a4/

Planning Engineer, TERP Asia Const. Corporation, The Emerald Hotel Resort and Casino

START Date
Experience Hours (Planning & Scheduling)
4000
  1. Participate in daily project meetings and discussions with the Project Management Consultant; including weekly progress meeting (per packages).
  2. Prepare and creates project baseline schedule based on the approved LOI (for newly awarded packages).
  3. Set work program and target milestones for each phase based on the project plan.
  4. Monitor and creates critical path based on the project schedule.
  5. Monitor day to day work progress and prepare monthly program and reports.
  6. Prepares the Labor histograms
  7. Monitors progress periodically and compares it w

Planning Engineer, TERP Asia Const. Corporation, The Emerald Hotel Resort and Casino

START Date
Experience Hours (Planning & Scheduling)
4000
  1. Participate in daily project meetings and discussions with the Project Management Consultant; including weekly progress meeting (per packages).
  2. Prepare and creates project baseline schedule based on the approved LOI (for newly awarded packages).
  3. Set work program and target milestones for each phase based on the project plan.
  4. Monitor and creates critical path based on the project schedule.
  5. Monitor day to day work progress and prepare monthly program and reports.
  6. Prepares the Labor histograms
  7. Monitors progress periodically and compares it w

Planning Engineer, TERP Asia Const. Corporation, The Emerald Hotel Resort and Casino

START Date
Experience Hours (Planning & Scheduling)
4000
  1. Participate in daily project meetings and discussions with the Project Management Consultant; including weekly progress meeting (per packages).
  2. Prepare and creates project baseline schedule based on the approved LOI (for newly awarded packages).
  3. Set work program and target milestones for each phase based on the project plan.
  4. Monitor and creates critical path based on the project schedule.
  5. Monitor day to day work progress and prepare monthly program and reports.
  6. Prepares the Labor histograms
  7. Monitors progress periodically and compares it w

Planning Engineer, TERP Asia Const. Corporation, The Emerald Hotel Resort and Casino

START Date
Experience Hours (Planning & Scheduling)
4000
  1. Participate in daily project meetings and discussions with the Project Management Consultant; including weekly progress meeting (per packages).
  2. Prepare and creates project baseline schedule based on the approved LOI (for newly awarded packages).
  3. Set work program and target milestones for each phase based on the project plan.
  4. Monitor and creates critical path based on the project schedule.
  5. Monitor day to day work progress and prepare monthly program and reports.
  6. Prepares the Labor histograms
  7. Monitors progress periodically and compares it w

/ Construction Project Planner / Senior Planner, Crown House Technologies (Laing O'Rourke), LD4.2

START Date
END Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
1000

Lead MEP Project Planner

Have been involved in building data centres from concept to soft hand over on 60mega watts

Projects in slough, London:

 Assist project planner in updating the MEP section of the programme based on the latest design (post tender

design) information

 Discuss and help project planner in setting up regular reporting, production reports, KPIs to allow the site

team to understand the project position in relation to current progress