At the time, this project was the biggest in Europe. I worked for the Formation Cost & Control Manager. The plans were in their infancy and they desperately needed their plans integrated with their costs. I developed a process to ensure the monthly reports corresponded to the plans and were consistent. Extensive use of Email, Word, Excel, MS Project and Artemis. Artemis International sub-contracted me for this contract as one of their consultants.

Stephen Willey

First Name
Stephen
Last Name
Willey
Professional Since
Oldest experience
Years Experience
14

I have always worked in and around projects but only recently have i been directly involved with them (last 3 - 4 years).  Most of my early work experience has been around sales and customer support, becoming more involved with projects as my support experience grew.

I am analytical by nature and this is what has taken me towards the planning side of things and is something i enjoy greatly.

I am also completing an Open University Mathematics Degree to help assist with my analytical skills and career progression

Senior Planner, Chief Engineer, Amey Construction Ltd, Manchester Airport Aprons & Taxiways

START Date
END Date

Senior Planning Engineer Manchester Airport Aprons & Taxiways - Design & build – Extension to existing Aprons & Taxiways, involving extensive Mechanical & Electrical works and Pavement Quality Concrete. Quality Systems Manager, Planner & Design Manager, Engineering Team Leader.

Project Controller, Thales Avionics Ltd, (various projects)

START Date

Project Controller for Thales Avionics inclding the following tasks and resposibilities:-

The creation of the initial Programme Plan that included all deliverable Milestones, Internal Milestones and any other feature that will require to be delivered by the Programme

Generate, maintain and monitor the progress of Work Packages released to support Programme execution

Update budgetary and resource information held within the schedule with actual and analyse cost variation(s).

PMC Project Planner/Scheduler, Fluor Mongolia, Oyu Tolgoi Gold and Copper Mining Project

START Date
END Date
Experience Hours (Planning & Scheduling)
3000

Program Management Contractor’s Planner/Scheduler that oversees the Contractor’s project control functions which includes but not limited to:

Lead Planner / Senior Planner - London., Atkins, Heathrow T2A

START Date
END Date

BAA T2 Radio Integrator (Heathrow Terminal 2) – Airports / Communications, Jan 2011 – date
Lead planner on this project that forms part of the new build of Terminal 2 project. This includes building baseline programmes, creating a system of reporting to comply with BAA requirements, monthly updates, advising management on PC issues, delay analysis and EVM performance figures.